02/01/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
02/06/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A0.0: Please provide an architectural site plan in this set of drawings. 2. Sheet A0.1; Occupancy and Exit Calculations (Exits Required): Although no occupant load calculations are required for this shell permit, the first line under Exits Required indicates 207 total occupants. Please revise or remove this number. 3. Sheet A0.1; Occupancy and Exit Calculations (ADA Exits Required): Although no occupant load calculations are required for this shell permit, the second line under ADA Exits Required indicates 8 ADA Exits provided. Please revise or remove this number. 4. Sheet A0.1; Occupancy and Exit Calculations (Travel Distance): Although no occupant load calculations are required for this shell permit, the third line under Travel Distance indicates 30' maximum travel distance to exits. Please revise or remove this number. 5. Sheet A0.1; Occupancy and Exit Calculations (Suites 201, 301, 303, and 306): These suites are not pertinent to this permit. Please revise or remove those suites. 6. Sheets A1.0, A2.0, A3.0, S1.1, and S2.1; Plans: Please coordinate the north arrows on these plans. 7. Sheet A1.0 (Floor Plan); Sheet A4.0 (Elevations): The reference elevation directions do not match the floor plan directions. Please coordinate. 8. Sheet A1.0; Key Notes: Note 23 references a site sheet that is not included in this permit. Please revise or remove the reference. 9. Sheet A1.0; Floor Plan: Near gridlines 1 and A and 2 and A , a detail at the roof drains indicates 8/A7.2. Please verify. 10. Sheet A2.0; Ceiling Plan (Key Notes(: Note 2 indicates trellis with 3x3x1/4 steel angles. Please coordinate the framing sizes with structural sheet S2.1 (Roof Framing Plan). 11. Sheet A3.0; Roof Plan (Key Notes): Note 4 indicates trellis with 3x3x1/4 steel angles. Please coordinate the framing sizes with structural sheet S2.1 (Roof Framing Plan). 12. Sheet A3.0; Roof Plan: This plan indicates a wall height of 19'-0" at the Drive-Thru, while the elevation on Sheet A4.0 indicates 19'-4". Please coordinate. 13. Sheets A4.0, A5.0, and A6.2: Notes: Note 8 indicates trellis with 3x3x1/4 steel angles. Please coordinate the framing sizes with structural sheet S2.1 (Roof Framing Plan). 14. Sheets A4.0 through A6.3; Sections: Please verify all top of wall elevations with Sheet A3.0 15. Sheet A5.0; Building Sections: Where are Building Sections 1 and 2 cut on a plan, or referenced in a note? Please verify. 16. Sheet A5.0; Building Section 2: The wall on the right side of the section indicates a 18'-0" parapet height? Where does that occur on Sheet A3.0? 17. Sheet A6.2; Wall Section 3: A note indicates indicates trellis with 3x3x1/4 steel angles. Please coordinate the framing sizes with structural sheet S2.1 (Roof Framing Plan). 18. Sheet A7.2; Detail 12: This detail indicates a stud partition at the roof ladder. Please revise the wall to masonry. 19. Sheet A7.2; Detail 12: Per the IBC Section 1015.7, since the roof hatch opening is less than 10 feet from the roof edge, guards shall be provided using the construction requirements of Sections 1015.3 and 1015.7. 20. General: Please provide the Special Inspection Certificate with Parts A and B completed. 21. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
02/08/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. An approved development plan is not to be used for construction of on-site utilities (e.g. water service to the building, building sewer, etc.). Provide the civil plans showing the installation of the water service to the building and the installation of the building sewer as part of the building plan set. Reference: Sections 104.2 and 107.2.1, IBC 2018. 2. Verify the water pressure available to the site. Per Tucson Water, the water pressure range for this address will be approximately 76 to 83 PSI. Provide a water pressure regulator conforming to ASSE 1003 or CSA B356 to limit the water pressure to 80 PSI or less. Reference: Section 604.8, IPC 2012. |
02/08/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. In the COMcheck Envelope Compliance Certificate, the more efficient HVAC pe4rformance option was selected as the additional efficiency package requirement to comply with Section C406, IECC 2018. In the Mechanical Compliance Certificates, however, the additional efficiency package requirement is "unspecified". Coordinate the approach to be used to comply with Section C406.1, IECC 2018. Note: the rooftop units are "unitary air conditioners" with gas-fired heating sections, shown in Table C403.3.2 (1), IECC 2018. 2. Revise the COMcheck energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing (e.g. heated and insulated slab on grade, glass area and glazing calculations, number and type of doors, wall area, continuous insulation on all walls, etc.). Reference: Section C303.1, IECC 2018, as amended by the City of Tucson. 3. Correct the drawing scales shown on the architectural floor and roof plans. |
02/08/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
02/21/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. I.D. the panel A and B designation on the one line diagram so that it correlates with the panel schedules and the floor plans. 2. Clarify whether MLO or Main Breaker on the panel schedules. 3. Indicate how panel LB is fed from or thru panel LA. 4. Provide complete compliance with the 2018 IECC for lighting. If the interior lighting is intended to be temporary please provide a note on the plan that states this and also that the interior lighting will be addressed in the TI permit. Ref; 2018 IBC 107.2.1, 2017 NEC. 2018 IECC |
02/26/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T19CM00589 - New Building (Commercial - Food Service) Building Plan Review (1st Review) Starbucks 65 W. River Road - C-2 Zoning TRANSMITTAL DATE: February 26, 2019 DUE DATE: February 26, 2019 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has reviewed the building plans for compliance with the approved development package. While the building footprint and the site revisions are consistent with the approved DP as it relates to the zoning review purview of the Building footprint, Height, square footage, site conditions etc., zoning cannot approve the building plans until the PDSD Commercial Plans reviewers have approved the building plans. 2. COMMENT: If any changes are necessary, due to the PDSD Commercial Plan Reviewer's comments that affect or change the building footprint, height, or square footage, the DP will need to be updated prior to approval of the building plans by Zoning. 3. COMMENT: Once the plans have been reviewed and approved by the PDSD Commercial Plan Reviewers and zoning has verified consistency with the DP, the building plans can be approved by zoning. If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised building plans |
02/27/2019 | LOREN MAKUS | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/25/2019 | PMARTIN1 | APPROVAL SHELF | Completed |
03/25/2019 | PMARTIN1 | OUT TO CUSTOMER | Completed |
03/25/2019 | PMARTIN1 | REJECT SHELF | Completed |