Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T19CM00339
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 02/04/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. PZSE Structural Calculations; Pages 10 through 13: Please provide full size drawings for the various array layout plans and the ballast quantities and locations. In addition, provide connection details for the arrays as required. 2. Schneider Structural Calculations: Please provide a full size drawing for the various array layout plans and the locations of the additional screws required for attachment of the PV panels to the roof. 3. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
| 02/05/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 02/11/2019 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Passed | |
| 02/14/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. REF; Riser and line diagrams. (a) Plan Sheet 2018092 shows the electrical service rated at 600 amps. The three -line diagram shows the service rated at 800 amps. Please clarify. (b) The picture of the existing service shows only three disconnect switches installed and the three-line diagram shows four and a main. Provide information on the plans to clarify the requirements needed to accommodate the installation of the additional switches. 2. Verify that the inverter is equipped with ground fault protection. Not specified on the spec sheet. NEC art 690.5. 3. Provide all the plan sheets as described on the drawing description on the cover sheet, and include the numbers on the drawings. 4. Provide the PV modules racking system details. 5. Provide grounding details for the racking system and modules. 6. Provide a permanent plaque or directory per NEC section 705.10 at each service on the premises. 7. Ref; Plan sheet 2018091 and the 3 -line diagram plan. (a) Identify all the areas where the PV modules are mounted apart from the roof area. (b) Are all the DC source circuits installed in EMT conduit as the wire schedule shows to the inverter? (c) The equipment layout shows 9 string home runs to the inverter and the 3-line shows 8. Please clarify. Ref; 2012 IBC sec 107.2.1, 2011 NEC art 230, 690, 705. |
| 02/14/2019 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | Revise on the site plan the annotation PROPOSED MULTI-PURPOSE BUILDING to "Exisitng Multi-Purpose Building Bldg. 4" |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/19/2019 | TWEIDEM1 | APPROVAL SHELF | Completed |
| 02/19/2019 | TWEIDEM1 | OUT TO CUSTOMER | Completed |
| 02/19/2019 | TWEIDEM1 | REJECT SHELF | Completed |