Plan Number: T18SE00064
Parcel: Unknown

Address:
10497 S SWAN RD

Review Status: Active

Review Details: REZONING - ZE HEARING

Plan Number - T18SE00064
Review Name: REZONING - ZE HEARING
Review Status: Active
Review Date Reviewer's Name Type of Review Description Status Comments
10/09/2018 ANY DOT ENGINEERING REVIEW Active
10/09/2018 JOSE ORTIZ DOT TRAFFIC REVIEW Active
10/15/2018 ANDREW CONNOR LANDSCAPE REVIEW Approved NPPO and Mitiagtion plans should be submitted with Development Package.
10/18/2018 MARTIN BROWN FIRE REVIEW Approved
10/22/2018 EHAMBLI1 ZONING REVIEW Completed CDRC TRANSMITTAL

TO: Development Services Department
Rezoning Section

FROM: Elisa Hamblin, AICP
Lead Planner

PROJECT: 10201 S Swan Rd
Parcel: 303-70-0005A
Zoning: RH Zone

T18SE00064
Mayor and Council Special Exception Procedure

TRANSMITTAL: October 22, 2018

The proposed utility use falls under UDC Article 4.8.3, Table 4.8-1: Permitted Uses - Rural and Suburban Residential Zones. Utility Land Use Group with Land Use Class/Type: Distribution System: Limited to Power Substation (Input Voltage of 115 Kilovolts or Greater) subject to Use Specific Standards 4.9.11.A.3, .6, .7, & .10 and 4.9.13.I.

Vehicular Access: = Vehicular access appears to be adequate
Vehicle Parking Required = 2 spaces per facility
Vehicle Parking Provided = 0
Short Term Bicycle Required = None required
Short Term Bicycle Provided = Not provided
Long Term Bicycle Required = None required
Long Term Bicycle Provided = Not provided
Off-Street Loading Required = None required
Off-Street Loading Provided = Not provided
Pedestrian Access: = Pedestrian Access appears to be adequate
Allowed Building Height: = 30'
Proposed Building Height: = Equipment and structures up to 80'
10/31/2018 PMCLAUG1 ENGINEERING REVIEW Completed
10/31/2018 PMCLAUG1 ENV SVCS REVIEW Completed
10/31/2018 HEATHER THRALL SIGNS SIGN CODE REVIEW Completed
10/31/2018 PMCLAUG1 COMMUNITY PLANNING REVIEW Completed Background: This is a Special Exception request by TEP to construct a new 138/46/13.8 kV substation and associated facilities to facilitate solar development interconnection, provide future power supply for planned growth in the area, and provide contingency for the power system. The proposed site is a vacant 52.14 acre parcel south of the Swan Road and Old Vail Connection Road intersection. Swan Road is classified as Arterial Roadways on the Major Streets and Routes Plan map.

Surrounding Zoning and Land Uses: The property is surrounded by RH zoning to the north, east, south and west, with uses to the east - vacant land/prison, to the west - vacant and residences, to the north - vacant and gravel pit, and to the south - vacant, utility, and residential.


APPLICABLE PLAN POLICIES:

Plan Tucson: Supports the coordination with utility companies and other public service providers fort he planning of infrastructure, facilities, and services, making sure infrastructure and facility construction is sensitive in design and location to environmental and historic resources. PT also provides policy direction in the improvement and the appearance of above-ground utilities and structures, and supports extending access to high-tech wireless communications facilities throughout the city.

Note that the Rincon Subregional Plan does call out this site in any of the Map Details and thus does not provide for any specific land use policy guidance.

Analysis: Plan Tucson supports utility upgrades. The proposed project does not require a plan amendment.
10/31/2018 PMCLAUG1 TUCSON WATER NEW AREA DEVELOPMENT REVIEW Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW PARKS & RECREATION Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW OFFICE OF CONSERVATION & SUSTAINABLE DEVELOPMENT Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW PIMA ASSN OF GOVTS Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW PIMA CNTY WASTEWATER Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW SCHOOL DISTRICT Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW ADOT Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW TDOT RTA Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW TDOT STREETS Completed
10/31/2018 PMCLAUG1 REZ AGENCY REVIEW OTHER AGENCIES Completed