Plan Review Detail
Review Status: Completed
Review Details: PIA - SUBMITTAL
Plan Number - T18PI00033
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/02/2019 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Needs Review | |
01/02/2019 | FSHENK1 | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |
01/02/2019 | FSHENK1 | DOT PERMITS & CODES | REVIEW | Needs Review | |
01/02/2019 | FSHENK1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed | |
11/07/2018 | JIM FEMLING | DOT STREET MAINTENANCE | REVIEW | Completed | I do not have any comments for this project. Thanks, fs for JF |
11/13/2018 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Reqs Change | November 13, 2018 SUBJECT: Paving Plans for 36th Street - Park Avenue to Kino Boulevard PROJECT REVIEWER: Richard Leigh, TDOT, TDOT Eng. Review RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments and return redlined drawings with subsequent submittal. 1. Include the plan number "I-2016-007" in the title block of each sheet. 2. Include the PIA activity number "T16PI00033" on cover sheet. 3. Use TDOT engineering plan template for this plan set. The latest TDOT engineering plan template can be found at https://www.tucsonaz.gov/tdot/engineering. 4. Sheet 1: Add Arizona Blue Stake 811 label to cover sheet. 5. Sheet 2, General Paving Note 1: The City of Tucson has adopted the Pima Associates of Government (PAG) 2015 Standard Specification for Public Improvements (SSPI) and Standard Details (SD). Revise plan set to reflect this change. 6. Sheet 2, General Paving Note 2: Revise note to indicate the use of TDOT Mix No. 2 for the asphaltic concrete. 7. Sheet 6: Revise drawing to extend the pedestrian circulation path all the way to Kino Parkway Per Section C.2.4C.i.b.ii of the Bridges Planned Area Development document. 8. Indicate the closure of the existing curb opening located at Sta. 35+75, RT 36th St. 9. Please Refer to redline plans for additional comments and comment details. If you have any questions, I can be reached at 837-6647 or emailed at Richard.Leigh@tucsonaz.gov. |
11/19/2018 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | I am having a real problem with the asphalt connection to concrete at the east end of the project. Why isn't the 10' wide path carried through to Kino? Please make a note that all prickly pear must be planted a minimum of 5' off the pathway. |
11/27/2018 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Reqs Change | November 26, 2018 SUBJECT: T18PI00033 36th Street Widening PROJECT REVIEWER: Zelin Canchola, TDOT Review Section RESUBMITTAL REQUIRED: DOT Review Section has reviewed the PIA Plan for Traffic Engineering. The proposed plan requires the following change: Striping Plan: 1. Remove crosswalk striping at driveway intersections, including MLK 2. Eliminate yellow center turn lane striping at minor street intersections to create a gap. 3. Add - Show quantities of new striping, and signs. 4. Add required signs, including signs for the decal lane at MLK Jr. Way If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Needs Review | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Needs Review | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | COX COMMUNICATION | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | Emailed PE for clearance letters |
12/20/2018 | FSHENK1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | Emailed PE for clearance letters |