Plan Number: T18PI00016
Parcel: Unknown

Address:
4975 E BENSON HY

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T18PI00016
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/27/2018 RICHARD LEIGH DOT ENGINEERING REVIEW Reqs Change July 23, 2018

SUBJECT: Valencia Crossing Neighborhoods 3 & 4 Paving Plans.

PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section

RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval at this time. The following comments need to be addressed prior to in the subsequent review submittal. Please return redlined drawings with next submittal.

1. Use TDOT engineering plan template for this plan set. The latest TDOT engineering plan template can be found at https://www.tucsonaz.gov/tdot/engineering.

2. Include the plan number "I-2018-018" in the title block of each sheet.

3. Include PIA activity number "T18PI00016" on cover sheet.

4. Include Development and Subdivision number on cover sheet.

5. Storm Drain: Provide reinforced concrete pipe for the sections of storm drain proposed within the public rights-of-way per COT SDDM and include all details.

6. Provide complete details for the proposed rip rap at the outlets of sidewalk scuppers.

7. Sheet 3: Provide all details for the proposed catch basin a Sta. +/- 11+22, LT (Wash View Drive).

8. Provide curb access ramps at the intersections of Desert Peak Drive and Wash Overlook Drive and Deer Park Lane and Scenic Peak Way.

Please Refer to redline plans for additional comments and comment details.

If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsonaz.gov
07/30/2018 JIM FEMLING DOT STREET MAINTENANCE REVIEW Completed
08/06/2018 ZELIN CANCHOLA DOT TRAFFIC REVIEW Approved
08/07/2018 TWOLFGA1 PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
08/07/2018 TWOLFGA1 UTILITY CLEARANCES COT STREETS DIVISION Completed
08/07/2018 TWOLFGA1 PIA COORDINATOR OUT TO CUSTOMER Completed
08/07/2018 TWOLFGA1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES PC WASTEWATER MGMT Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES QUEST COMMUNICATION Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES COX COMMUNICATION Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES EL PASO NATURAL GAS Denied
08/07/2018 TWOLFGA1 UTILITY CLEARANCES KINDER MORGAN ENERGY Denied