Plan Number: T18PI00002
Parcel: Unknown

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T18PI00002
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/09/2018 LPETERS2 DOT PERMITS & CODES REVIEW Denied I have reviewed this plas and ahave the following comments:

1. Sheet 2 - Paving note 5 - This note should state, "Aspahlt Concrete shall conform to City of Tucson Mix #2."
2. Sheet 3 - Curb Ramp Details Please refernce PAG 2015 Access Ramp Details and Type.

No further comments.

Lance Peterson, P.E.
(520) 837-6777
02/01/2018 ZELIN CANCHOLA DOT TRAFFIC REVIEW Reqs Change February 1, 2018


SUBJECT: La Estancia Phase 8 T18PI00002 (I-2008-002)


PROJECT REVIEWER: Zelin Canchola,
TDOT Review Section

RESUBMITTAL REQUIRED: DOT Review Section has reviewed the PIA Plan for Traffic Engineering. The proposed plan requires the following change:

1. Add - Street name signs
2. Add - Stop signs
3. Add - No Parking fire access signs


If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov
02/13/2018 LINZUNZA UTILITY CLEARANCES COT STREETS DIVISION Denied
02/13/2018 GARY WITTWER DOT LANDSCAPE REVIEW Passed
02/13/2018 LINZUNZA UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
02/13/2018 CSALTZM1 DOT ENGINEERING REVIEW Denied SUBJECT: La Estancia De Tucson Phase 8 Public Paving and Drainage Improvements

PROJECT REVIEWER: Craig Saltzman, TDOT Engineering Review

RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to final approval. Please include a response letter addressing the following comments and return any redlined drawings with subsequent submittal.

1. Sheet 1: Include the plan number "I-2018-002" in the title block of each sheet.

2. Sheet 1: Include the PIA activity number "T18PI00002" on cover sheet.

3. Sheet 1: Location Map - Call outs for City of Tucson and Pima County need to be reversed. Example : The call out for the City of Tucson should be on the west side of the section line.

4. Sheet 2: Revise Paving Note 5 to indicate City of Tucson "City Mix" asphalt Mix #2.

5. Sheet 2: Revise Paving Note 10 to Read: The City shall not be held liable for any errors and/or omissions on these plans items not meeting City Standards. The errors and/or omissions shall be repaired and/or replaced at no cost to the City.

6. Sheet 2: Paving note 15: Revise phone number for Paul Rosenbloom to 520-791-3154.

7. Sheet 3: Detail A: Revise detail to reference placement of curb access ramps per PAG Standard Detail 207, Type 1.
8. Sheet 3: Detail B: Remove from detail the following: "Pedestrian Refuge".

9. Sheet 4 - 8: Indicate placement of survey monuments per PAG Standard Detail 103 at roadway intersections and at the points of curvature along roadway center line

9. Sht. 4: Mid-block access ramp at Sta. 157+80.05 move to Sta. 157+92.48 to align with the access ramp across the road.

10. Sht. 7: Profile - Street center grade - show % slope from the PVI Sta. 294+61.22 to Match Line

If you have any questions, I can be reached at 837-6621 or emailed at Craig.saltzman@tucsonaz.gov.
02/13/2018 LINZUNZA UTILITY CLEARANCES PC WASTEWATER MGMT Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES QUEST COMMUNICATION Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES COX COMMUNICATION Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES EL PASO NATURAL GAS Denied
02/13/2018 LINZUNZA UTILITY CLEARANCES KINDER MORGAN ENERGY Denied
02/23/2018 JIM FEMLING DOT STREET MAINTENANCE REVIEW Completed
02/23/2018 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
02/23/2018 LINZUNZA PIA COORDINATOR OUT TO CUSTOMER Completed