Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T18CM09766
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/14/2018 | NICHOLAS ROSS | ZONING | REVIEW | Approved | |
| 12/14/2018 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
| 12/14/2018 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Needs Review | |
| 12/14/2018 | NROSS1 | ENGINEERING | REVIEW | Passed | |
| 12/14/2018 | GPERU1 | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Please specify whether the mezzanine is existing; wall section F1 indicates a new wall to the bottom of the mezzanine deck. 2. SHT A1.1 Keynote 7 specifies a new steel railing at the mezzanine; provide an elevation detail for use of the steel railing for a required personel guard rail. 3. Specify the intended use for the mezzanine and provide the occupant load. IBC TABLE 1004.1.2 4. A minimum of 2 exits or exit doors is required from a room or space with an occupant load of 50 or more, which would apply to the Training Roof with an occupant laod of 57 persons. IBC 1015.1 5. Indicate the common path of egress travel from the mezzanine level.IBC 1014.3 6. Show the vertical grab bar above the horizontal grab bar for the water closets in accordance with 604.5.1 ICC A117.1 Please provide written responses to all plan review comments. |
| 12/14/2018 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 12/14/2018 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Clarify the scope of the plumbing work (e.g. new, relocated, or replacement fixtures). Relocated fixtures and appliances or fixtures that are being installed in new locations will require the new or revised piping to be shown. |
| 12/14/2018 | GPERU1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 12/17/2018 | MASHFOR1 | FIRE | REVIEW | Approved |