Permit Number: T18CM06809
Parcel: 13324010C

Address:
250 N MAGUIRE AV

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T18CM06809
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/31/2018 MARTIN BROWN FIRE REVIEW Approved
09/10/2018 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet S1.2; Foundation Plan: Note 2 was not located on the plan, and there is no Note 3 listed in the notes. Please verify.
2. General: Please provide written responses to all review comments.
09/10/2018 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
09/18/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
09/18/2018 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Clarify the extent of the security fencing for the chiller. Reference: Section 107.2.1, IBC 2012.
2. Provide a COMcheck Compliance Certificate for the chiller and cooling tower. Reference: Section C403.2.2, IECC 2012.
3. Identify the location for the termination of the refrigerant relief valve for the chiller. Reference: Section 1105.7, IMC 2012.
09/21/2018 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
09/25/2018 DAVID RIVERA ZONING REVIEW Reqs Change FROM: David Rivera
PDSD Zoning Review Section

PROJECT: T18CM06809 - Replace HVAC Cooler Tower and add Canopy Related DP18-0066
Building Plan Review (1st Review) Fellow Ship Square
250 N Maguire Avenue - O-3 Zone

TRANSMITTAL DATE: September 27, 2018

DUE DATE: September 25, 2018

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.

1. COMMENT: Zoning has reviewed the plans for compliance with the current approved version of the development package. While the proposed location is encroaching into the parking area to the north of the proposed changes. The drawings do depict the number of parking spaces that will be lost due to the modifications and it is not very clear if the existing parking structure will remain as is or be modified for the Chillers. A revision to the DP will have to be processed for review and approval. Once the DP has been reviewed and approved include a copy of the approved revised DP with the next submittal of these building plans.

2. Zoning will review the plans and verify that they are in compliance with the approved revision of the DP. In addition zoning cannot approve the building plans until the building plans have been approved by the PDSD Commercial Plans reviewers.