Review Details: COMMERCIAL - TI
Permit Number - T18CM06033
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/22/2018 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet A001-1B; Project Information: Please add the 2009 ICC/ANSI A117.1 Accessibility Code to this list. 2. Sheet A027-1B; Plumbing Calculations: In the first table, where did the load factors of Occupancy Group B (200) and Occupancy Group S (5000) come from? Please verify. The occupant load indicates 452 total. 3. Sheet A027-1B; Egress Code Exiting Calculation: This table indicates the correct load factors for Occupancy Group B (100), Occupancy Group A (15), and Occupancy Group S (300). The occupant load indicates 737 total. 4. Sheet A027-1B; Plumbing Calculations: In the third table, a total occupant load of 542 is indicated to determine the plumbing fixture counts. Should this match the first table? Please verify. 5. Sheet A027-1B; Plumbing Calculations: In the third table, the occupant load should be revised to match the first table under the Egress Code Exiting Calculation. Revise the required plumbing fixtures per the IBC Section 2902.1.1 for multiple occupancy groups. Please include the fixture calculations on this sheet for each Occupancy Group. 6. Sheet A027-1B; Occupancy Groups: Per the IBC Section 303.4, please indicate on this sheet the Occupancy Group A-3 to replace the A1, and revise the Occupancy Group S to S-1 per the IBC Section 311.2. The plumbing fixture calculations should use these Occupancy Groups to calculate the required plumbing fixtures per the IBC Table 2902.1. 7. Sheet A027-1B; Egress Code Exiting Calculation: The second table indicates 9 exits provided. The Life Safety Plan on this sheet indicates 10 exits. Please coordinate. 8. Sheet A027-1B; Egress Code Exiting Calculation: The second table indicates 36" for the required exit width. Please indicate on this sheet the required total exit width = 0.15 x total occupant load (per IBC Section 1005.3.2(Exception), and indicate the total exit width provided. 9. Sheet A101-1B; Demolition Notes: Note 2 is not in the Reference Notes, but shows up in two locations on the plan and are outside of the area in contract. Please verify. 10. Sheet A201-1B; Floor Plan: In the south area where the plan indicates the area is not included in the scope of work, a door marked BC0111A has an identifier of 2/A900. Is this door part of this permit, or should it be removed? 11. Sheet A201-1B; Key Notes: Notes 3, 4, and 6 were not located on the plan. Please verify. 12. Sheet A201-1B; Detail 5: A note on this detail indicates a 5'-0" maximum height from the sill to the wall cap. Section 2 is cut through the same wall as shown on Detail 5, but the sill height is indicated at 7'-0". Please coordinate. 13. Sheet A201-1B; Section 4: Please indicate the spacing of the diagonal brace at the top of the partition. 14. Sheet A211-1B; Equipment List; Power & Data Key Notes: The Equipment List item 1 was not located on the plan, and the Power & Data Key Notes 1 and 2 were not located. Please verify. 15. Sheet A301-1B; Details 3 and 4: Extend these details and indicate how the vertical studs are supported above. 16. Sheet A942; Detail 3: Extend the detail and indicate how the vertical studs are supported above. 17. General: Section R4-30-304 of the Rules of the Arizona State Board of Technical Registration requires that a notation shall be placed beneath the seal, written, typed, or electronically generated, that provides the day, month, and year of the expiration of the current registration. Please provide on all drawings. 18. General: Please provide written responses to all review comments. |
09/05/2018 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | As per the previous electrical plan review, it was requested to designated a branch circuit and panel for the lighting. There are still no breaker panel designations or panel schedule for the lighting. Also provide a written response. Ref 2012 IBC 107.2.1, 2011 NEC 408.4. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/14/2018 | QJONES1 | APPROVAL SHELF | Completed |
09/14/2018 | QJONES1 | OUT TO CUSTOMER | Completed |
09/14/2018 | QJONES1 | REJECT SHELF | Completed |