Permit Number: T18CM05904
Parcel: 11504334A

Address:
328 E HELEN ST

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T18CM05904
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/07/2018 MARTIN BROWN FIRE REVIEW Approved
08/09/2018 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. Sheet A0.2; Summary of Governing Regulations: The accessibility code should indicate the 2012 IBC with the 2009 ICC/ANSI A117.1. Please revise.
2. Sheet A0.2; General Building Summary: The allowable building area should indicate 27,000 SF/story (per the allowable area calculation on this sheet). Please revise.
3. Sheet A0.2; General Building Summary: Please separate the first and second floor areas, and indicate the occupant load calculation on this sheet. Sheet A0.3 (Chapter 3) indicates there will be children meeting the requirements of Section 305.2 (Group E) and Section 308.6.1 (Group I-4), along with Groups S-1 and B. Please provide a breakdown on this sheet of the occupant loads for each group.
4. Sheet A0.2; Required Plumbing Fixtures: The required plumbing fixtures on this sheet must be calculated for the occupant loads established for each use. There are different requirements in Table 2902.1 for E, I-4, S-1, and B occupancy groups. Please include calculations on this sheet for each of those groups. The IBC Section 2902.1 indicates plumbing fixtures shall be provided for the type of occupancy use.
5. Sheet A0.2; Required Plumbing Fixtures: The drinking fountain indicates 1/100 is required, and one is provided. Is the drinking fountain a high/low unit (was not located on architectural or plumbing plans). Please verify the location of the drinking fountain, and verify the required units for 126 occupants.
6. Sheet A0.3; Chapter 5: The sum of the first and second floor areas listed do not agree with the total square footage indicated (11,039 SF). Please verify.
7. Sheet A0.3; Key to Occupancy Groups: The First Floor Plan does not indicate any Group E area according to the Key to Occupancy Groups (shaded grey). The occupant loads on the First Floor Plan are calculated using Table 1004.1.2 for daycare only. Please clarify.
8. Sheet A0.3; Key to Occupancy Groups: This key includes business, but no area on the plan uses the calculation for business per Table 1004.1.2. Please clarify.
9. Sheet A0.3; Chapter 11: This section references Figure 404.2.3.1 in the ANSI A117.1 for clear floor area. Please revise that reference.
10. Sheet A0.3; Applicable Codes: Please remove the reference to the 2010 ADAAG, and indicate the ICC/ANSI A117.1 (2009 edition).
11. Sheet A0.3; Chapter 3: Please indicate the occupancy classification I-4 (Section 308.6) for the daycare facilities for children less than 2 1/2 years of age. It may be classified as an E, but the actual use (Child Day Care) falls under Section 308.6.
12. Sheet A0.3; First Floor Plan: A bold dashed line on the plan indicates a one hour fire rated wall. The Chapter 5 analysis indicates "Per 508.3, non-separated uses". Please clarify.
13. Sheet D1.0; Demolition Keynotes: Note 6 was not located on the plan. Please verify.
14. Sheet D1.1; Phase 2 Demolition: When does the Phase 2 demolition begin? Is it a part of this project, or does it commence after this project is completed? Please clarify on this sheet.
15. Sheet D1.1; Demolition Keynotes: Note 8 was not located on the plan. Please verify.
16. Sheet D3.0; Demolition Key Notes: Note 9 was not located on the elevations. Please verify.
17. Sheet A2.0; Wall Type Notes: In Note F, please reference the Detail 12/A9.0 and the bracing sizes note (at the end of the Wall Type Notes).
18. Sheet A2.0; Floor Plan: In Room 106, a Keynote 2 typ. is indicated at a table and chair. Please revise the note (should it be note 15?).
19. Sheet A2.0; Keynotes: Note 8 references Detail 5/A1.2 Delta 4 for the Family Center. Please revise the reference.
20. Sheet A2.0; Keynotes: It appears Note 19 is missplaced on the plan (should it be Note 18?). Please verify and add Note 19 to the correct location on the plan.
21. Sheet A2.0; Floor Plan: At Gate 199A (near outdoor play area), Elevations 7/A5.2 and 8/A5.2 are shown. There is no Elevation 7 or 8 on Sheet A5.2. Please verify.
22. Sheet A5.0; Accessibility Elevations: Please indicate dimensions for the position of grab bars from walls per the ICC/ANSI Figures 604.5.1, 604.5.2, and 609.4.2, or reference drawings on Sheet A9.0. Please verify the references for Sheet A9.0 include adult and children positions for the grab bars.
23. Sheet A5.3; Section 1: The City of Tucson requires all lettering (upper and lower case) to be a minimum of 3/32" in height. Please revise.
24. Sheet A6.0; Reflected Ceiling Plan Keynotes: Note 3 indicates a one hour rated ceiling. Please verify this is required.
25. Sheet A6.0; Reflected Ceiling Plan Key: The emergency exit lighting is not indicated on the plan. Please verify.
26. Sheet A6.0; Reflected Ceiling Plan Key: A note indicates a dashed line is for a one hour rated wall to deck. Please verify this is required.
27. Sheet A8.0; Door Schedule: Notes to the Door Schedule indicate to see the Door Hardware Specifications for hardware sets. Please reference in this note where those specifications are located.
28. Sheet S1.0; Design Loads: Since the attic area is used for storage, does the 60 PSF uniform live load for elevated platforms meet that loading requirement? Please verify.
29. General: Please provide a Special Inspection Certificate for masonry construction, epoxy anchors, and expansion anchors.
30. General: Please provide written responses to all review comments.
08/20/2018 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Clarify the configuration of the 24" x 10" return grille with a fire damper shown near column 1.9-D on sheet M1.0. How does the return air get to the HVAC unit? Is it supposed to be connected to the 24" x 10" return air duct shown near column 2.3-D on sheet M1.1?
2. Secure the refrigerant circuit access ports of the condensing units to prevent unauthorized access. Reference: Section 1101.10, IMC 2012.
3. Demonstrate energy code compliance for the alterations to the building envelope based on the current code. Specify the required U-factors and Solar Heat Gain Coefficients (SHGC) for the fenestration and doors on the architectural drawings. Reference: Sections C101.4.3, C101.5, C103.2, C303, and C401.2.1, International Energy Conservation Code 2012.
08/20/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Revise the piping layout shown in detail D/P1.0 for P-1, P-1A and P-2B and similarly P-1A and P-2A in detail A/P1.0. A plumbing vent may not be used for any purpose other than venting of the plumbing system (e.g. the horizontal drain for P-1A is connecting to the vent for P-2B). Reference: Section 901.4, IPC 2012.
2. Clarify the connection of the existing water softener to the existing cold water piping in detail A/P1.1 (i.e. coordinate the detail with detail 209). Note: should keynote #11 on P1.1 be referring to the relocated water softener? Reference: Section 107.2.1, IBC 2012.
08/20/2018 ROBERT SHERRY WATER REVIEW Completed
08/21/2018 DAVID RIVERA ZONING REVIEW Reqs Change FROM: David Rivera
PDSD Zoning Review Section

PROJECT: T18CM05904 - Casa De Los NiƱos
Building plans (1st Review) T.I. Child Care
328 E. Helen Street - PAD 20 Zoning

TRANSMITTAL DATE: August 21, 2018

DUE DATE: August 29, 2018

COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.


1. COMMENT: Zoning has reviewed the building plans but cannot approve them at this time. The proposed modifications to the interior do not affect any zoning requirements and the use of the building and site is not changing.

2. COMMENT: In addition, the building plans must be approved by the PDSD commercial plans reviewers before zoning can approve the plans.


3. COMMENT: Once the plans have been approved by all PDSD Commercial Plans reviewers and no site changes are made that affect zoning requirements, zoning will stamp and sign the building plans as it pertains to the zoning review purview.

If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email at David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov
08/27/2018 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
#1. Ref; Plan Sheet E0.1. Comcheck for the lighting is not complete.
#2. Ref; E1.0. It appears the existing exterior lighting was not included in the lumen calcs.
#3. Ref; Plan Sheet E2.1. There are 2 EF's Labeled as EF4 on the plan.
Ref: 2012 IBC sec 107.2.1, 2011 NEC.

Final Status

Task End Date Reviewer's Name Type of Review Description
09/18/2018 QJONES1 APPROVAL SHELF Completed
09/18/2018 QJONES1 OUT TO CUSTOMER Completed
09/18/2018 QJONES1 REJECT SHELF Completed