Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - TI ALL
Permit Number - T18CM05254
Review Name: RESUBMITTAL - TI ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/28/2018 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved | |
08/31/2018 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Approved | |
09/05/2018 | NROSS1 | ZONING | REVIEW | Approved | |
09/11/2018 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. The plumbing fixture schedule still specifies a non-metering faucet. Revise the specification to coordinate with the notes and the applicable code sections. [Initial comment: Provide automatic faucets for the lavatories, dispensing a maximum of 0.25 gallons per metering cycle. Verify that the duration of the automatic faucet cycle will be at least 10-seconds for accessibility. Reference: Section 416.6, IPC 2012, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-09.] 2. The plumbing fixture schedule still specifies a thermostatic mixing valve that complies with ASSE 1016. Not all mixing valves comply with both ASSE 1016 and ASSE 1070; revise the specifications to note the correct ASSE standard to prevent the substitution of an incorrect mixing valve. [Initial comment: The temperature mixing valve specified for use with the public lavatories is listed as conforming to ASSE 1070, not ASSE 1016. Revise the specifications to note the correct ASSE standard so that an incorrect mixing valve is not substituted. (Note that the Watts USG-B has been discontinued; the replacement is the Watts LFUSG-B.) Reference: Sections 416.5 and 607.1.2, IPC 2012.] 3. Correct the configuration of the cleanout downstream of the grease interceptor (keynote 6) to allow cleaning in the direction of flow. Reference: Section 708.5, IPC 2012. [Initial comment: Clarify why the sample vault for the gravity grease interceptor is located upstream of the interceptor. Reference: Section 107.2.1, IBC 2012.] |
09/12/2018 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. The revised COMcheck envelope compliance certificate does not correspond to the building shown in the drawings for the building components or the wall and storefront areas. Show how you plan to add continuous insulation to the roof.[Initial comment: Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing. The drawings for the shell building variously indicate that the roof was built with R-21, R-30, or R38 cavity insulation and no furring for the exterior walls. The new drawings show no furring of the exterior walls in the dining area, no continuous insulation for the roof or the exterior walls, and no clear specification for the new cavity insulation for the dining room roof. Clarify how the finished suite will be insulated. Reference: Section C303.1, IECC 2012, as amended by the City of Tucson.] 2. The heat pump schedule on sheet M2 does not show economizers for the four heat pumps. Coordinate the drawings and schedules with the COMcheck mechanical compliance certificate. [Initial comment: Revise the COMcheck mechanical compliance certificate using HVAC components that correspond to those shown on the drawings (there are two 5-ton and two 6-ton heat pumps without economizers, not 4 2-ton heat pumps with economizers).] 3. Note #10 in the mechanical equipment schedule on sheet M1 still shows 3266 CFM supplied by MAU-1. [Initial comment: The sum of the outside air (2830 CFM) and make-up air (3266 CFM) flow rates significantly exceeds the exhaust air (4120 CFM) flow rate. Show how over-pressurization building will be avoided. Reference: Section 501.4, IMC 2012.] 4. The hood canopy for the conveyor pizza oven still does not extend 6" beyond the oven. [Initial comment: Hood canopies shall extend at least 6" horizontally on all open sides beyond the edge of the top horizontal surface of the appliances under the hood (see the pizza hood). Reference: Section 507.12, IMC 2012.] 5. Correct the spelling in note #10 in the mechanical equipment schedule on sheet M1 from "RETICULATING" to "RECIRCULATING". [Initial comment: Verify that the evaporative cooling section of the makeup air unit specified on sheet M5 is equipped with a recirculating water system. Reference: Section 928.2, IMC 2012 and ARS Title 45, Chapter 1, Article 12. See text at: (http://www.azleg.gov/viewdocument/?docName=http://www.azleg.gov/ars/45/00313.htm).] |