Permit Number: T18CM04740
Parcel: 107040130

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T18CM04740
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/19/2018 GPERU1 BUILDING-COMMERCIAL REVIEW Reqs Change 1. Please provide the types of occupancies for the existing temant spaces within the building.
2. For non-separated use calculations the most restrictive occupancy must be used for the base allowable area. Provide allowable area calculations using the most restrictive occupancy.
3. Label all required exits from the tenant space.
4. Provide a door schedule and include hardwate types.
5. Provide a wall schedule for all new wall installations.
6. Provide construction details for all new wall construction; detail connections at the roof and floor.
7. Access to restroom facilities is required for the tenant space; facilities must be under the same management as the tenant space.
8. Provide dimensions on the floor plan of the TI,
9. The classificatiion for the tenant improvement is listed as a storage use (S-2); provide a description of the types of materials or stock that will be stored.
10. Provide minimum plumbing fixture requirements for the T.I.
11. Provide a list of interior finish materials.
12. Specify the types of walls separating tenant spaces.
06/19/2018 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change Provide a mechanical design (e.g. ventilation, refrigeration equipment, condensate drainage).
06/19/2018 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
06/19/2018 ROBERT SHERRY WATER REVIEW Reqs Change 1. Provide the size, serial nimber, and the demand served by the existing water meter.
2. Provide the size and type of backflow preventer associated with the water meter.
06/19/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Passed
06/26/2018 SVALENZ1 ENGINEERING REVIEW Needs Review
06/26/2018 SVALENZ1 ZONING REVIEW Needs Review
06/26/2018 SVALENZ1 FIRE REVIEW Needs Review
06/26/2018 SVALENZ1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review