Permit Number: T18CM02367
Parcel: 10508015F

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T18CM02367
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/09/2018 MARTIN BROWN FIRE REVIEW Approved
04/20/2018 ROBERT SHERRY WATER REVIEW Reqs Change Provide the serial number and size of the water meter that will be supplying water to this building and total demand that the water meter is serving.
04/23/2018 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Approved
04/23/2018 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Show the size, routing, and termination of the condensate drains for the three new heat pumps. Reference: Section 307.2.1, IMC 2012 as amended by the City of Tucson.
2. Provide ventilation (exhaust) for the new restroom, 213. Verify that sufficient outside air is introduced into room 212 to accommodate the required exhaust flow rate. Reference: Section 403.2.2, IMC 2012.
3. Clarify how the balancing contractor is to set the air flow rates for the existing HVAC system located near column C-2 after you have deleted one diffuser and replaced another; Outside air requirements? Reference: Section 403.2, IMC 2012.
4. Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing. Reference: Section C303.1, IECC 2012, as amended by the City of Tucson.
5. Provide NFRC fenestration product ratings for the Solar Heat Gain Coefficient (SHGC) on COMcheck per footnote b of the envelope assembly descriptions or use the appropriate default SHGC from Table C303.1.3 (2), IECC 2012.
6. Revise the heating and cooling load calculations, using the exterior design conditions shown in Section 302.2, IECC 2012, as modified by the City of Tucson.
04/23/2018 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed
04/23/2018 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change T18CM02367

1. Sheet T1; Please provide on this sheet the plumbing fixture calculations for the Showroom Building addition, including water closets, lavatories, drinking fountains, and service sinks. Use the IBC Table 2902.1. Verify the existing fixtures adequately meet the requirements of the existing occupant load and the addition occupant load.
2. Sheet A2.3; Ground Floor Plan: At the north wall of the building addition, a 6'-0" wide area is designated as M1. Please indicate on the plan what this represents, or add a reference note as an explanation.
3. Sheet A2.4; Second Floor Plan: Please complete the enlarged plan reference at the west stair.
4. Sheet A2.5; Exterior Wall Reveal: Please revise the detail reference number so this detail and an elevation on this sheet do not have the same number.
5. Sheet A2.5; Elevations 1 and 2: Please add the grid lines to the elevations.
6. Sheet A2.6; Building Section C: Please finish the detail reference for the vertical reveal between grids D and E.
7. Sheet A2.7; Section 3: Please provide the metal stud sizes and spacing in this section, or add a reference note for that information.
8. Sheet A2.7 (Section 1); Sheet A2.4 (Second Floor Plan): Section 1 indicates a second floor elevation of 113'-0" (same as the second floor plan), while the dimensions on Section 1 indicate 12'-0" from finish first floor to finish second floor. Please coordinate.
9. Sheet A2.8; Second Floor Stair Plan 7: On the west end of the stair, a duct chase is indicated. The IBC Section 713 requires a shaft enclosure to be constructed as a fire barrier with a one hour fire resistance rating. Please indicate that on the plan. In addition, indicate the wall construction and provide the U.L. listing number for that assembly.
10. Sheet A2.9; Door Schedule: Please reference Sheet SP3 for the door hardware schedule.
11. Sheet A2.9; Window Elevation W1: This elevation indicates the second floor is at elevation 113'-8". Please coordinate.
12. Structural Calculations; Showroom Addition: Structural calculations were not located for the new steel columns and footings at the Showroom addition (pages 58-71). Please verify.
13. Structural Calculations; Pages 69-71: Where is this existing 6x6x5/8 steel tube column located on the plan? Please verify.
14. General: Please provide written responses to all review comments.
04/26/2018 MMORENO1 ZONING REVIEW Reqs Change FROM: Michael Moreno
PDSD Zoning Review Section
PROJECT: T18CM02367 - Tenement Improvement
Building Plan Review (1st Review) Tucson Subaru
4901 N Oracle Rd.
TRANSMITTAL DATE: April 26, 2018
DUE DATE: April 26, 2018
COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed.
1. COMMENT: Zoning has reviewed the building plans for compliance with the approved development package. While the building footprint and the site revisions are consistent with the approved DP as it relates to the zoning review purview (Building footprint, Height, square footage, site conditions etc) zoning cannot approve the building plans until the Commercial Plans reviewers have approved the building plans.
2. COMMENT: The development package sheets provided in the building plan set should either be the approved set or marked as reference; or removed from the building set completely and submitted as a reference copy of the approved and signed development package.
3. COMMENT: Once the plans have been approved by all Commercial Plans reviewers and no site changes are made that affect zoning requirements, zoning will stamp and sign the building plans as it pertains to the zoning review purview.
If you have any questions about this transmittal, Contact Michael.Moreno@Tucson.az.gov at any time during the week
04/27/2018 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please address the following electrical plan review comments. Also provide a written response.
#1. Ref: Plan Sheet EL103. Outdoor Lighting.
(a) As noted, full cut-off under canopy lighting is exempt from lumen calcs, however not from light source color temperature requirements (3500K). Please verify. Section 402.1.
(b) A special inspection will be required outdoor lighting per section 106.2.1. Comply with section 104.2.2
(c) Could not refer to project # M3-PN124055 for the existing lumen calcs. Provide a permit or activity number if available. Otherwise provide a lighting site plan with the locations and complete inventory of all exterior luminaires.
#2. The electrical site plan ES101 does not correlate with the Architectural plan AS1. Provide an electrical site plan that clearly shows the locations of the proposed New Service and Shop Buildings include the Showroom.
#3. Provide 2012 IECC compliance fo lighting.
Ref: 2012 IBC sec 107.2.1, Tucson/Pima County Outdoor Lighting Code.
05/04/2018 LOREN MAKUS ENGINEERING REVIEW Approved