Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/09/2018 | MARTIN BROWN | FIRE | REVIEW | Approved | |
04/18/2018 | ERIC NEWCOMB | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Verify the peak electrical demand from the utility company; submit electrical load calculations for derating the main circuit breaker. NEC 220.5 2. Provide specifications on electrical terminations, breakers and equipment for 90 degree rating on insulation. NEC 110.14(C)(1) 3 Provide a grounding detail for the panel racking system; submit panel racking installation specs. NEC 690.41 4. Provide clear, readible copies of equipment electrical data sheets; type is too small. 5. Provide a trench detail for the use of area and indicate depth. NEC 70-208 6. An AC disconnecting means shall be mounted within sight of the inverter(s). NEC 690.14 7. Provide specifications for mounting inverters; indicate location and height of inverter above walking surface. NEC 690.14 8. Provide inverter specifications for ungrounded system. NEC 690.35 9. Provide SE conductor size for verification of No. 4 AWG copper bond wire at combiner panel and SES. NEC TABLE 250.66 |
04/18/2018 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
05/01/2018 | BLARSON1 | OUT TO CUSTOMER | Completed |