| 03/04/2019 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 03/05/2019 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet Cover; Building Code Analysis (Building Area); Floor Area Calculations: The note at the Building Area indicates the total building area, excluding porches, is 26,668 SF, while the Floor Area Calculations indicates 24,645 SF. Please verify. 2. Sheet Cover; Building Code Analysis (Building Area); Floor Area Calculations: The Building Area indicates a total area of 26,668 SF (which includes all porch areas), while the Floor Area Calculations indicates a total building area of 24,645 SF + total porch area of 2052 SF = 26,697 SF. Please verify. 3. Sheet A1; Floor Plan: Please clarify the building section indicator next to Section H/A12 cut. 4. Sheet A2; Second Floor Plan: From the initial plan review, the new second floor area was 313 SF, and the new mezzanine area was 1293 SF. The revised plan indicates the second floor area is 15,521 SF, and the new mezzanine area is 2044 SF. This will add 208 + 751 SF to the original valuation. Please verify these numbers are correct. 5. Sheet A2: The new area (208 + 751 SF) will also be added to the original impact fee. Please verify these numbers are correct. 6. Sheet S3; Foundation Plan: Is there a footing schedule for the F2 and F4 footings indicated on this plan, or are the footing sizes and reinforcing indicated typically on the sections cut through the footings? Please verify. 7. Sheet S3; Foundaton Plan: At the new stair landing, there is a footing F4 indicated with a Section 1/S13 cut. Please indicate the Section cut 1 on the correct section on Sheet S13. 8. Structural Calculations: Please provide a key plan in the calculations that locates and clarifies the structural foundation sizes and framing members for this review. 9. General: Please provide written responses to all review comments. Reviewed by Eric Newcomb Contact at 520-837-4911 or Eric.Newcomb@tucsonaz.gov |
| 03/19/2019 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the gas pipe note located on sheet P2 that calls for routing a "1-1/2"G up to ceiling place" while the drawings shows a 2"G running up to the roof. 2. Verify the developed gas pipe length for AC-1. The diagram on sheet P6 shows 234' but the drawing on sheet P2 shows AC-1 about 15' further from the meter than AC-4 which has a developed pipe length of 268'. |
| 03/19/2019 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. 1. Ref; Plan Sheet E0.1. Provide for a time clock that will maintain the time and program for a minimum of 6 hours. OLC sec 403.5.1 2. Unshielded luminaire output cannot exceed 3000 lumens. OLC sec 401.4. 3. If the flagpole luminaires are in the scope of work, include them in the lumen calcs and Light Fixture Schedule. Verify compliance with sec 401.4 and 402.1 OLC. 4. Provide a note on the plans requiring a special inspection for outdoor lighting. OLC sec 104.2.2 and 106.2.1 5. What does the EXEMPTION percentages column represent in the lumen calcs? How can some luminaires be 50% exempt? Please clarify with OLC sections. Ref; 2012 Tucson/Pima County Outdoor Lighting Code (OLC), 2012 IBC sec 107.2.1. |
| 03/20/2019 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 03/20/2019 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C302.2, C403.2.1, and C403.2.2, IECC 2012 as amended by the City of Tucson, and Section 312.1, IMC 2012. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 04/12/2019 | AMARTIN1 | OUT TO CUSTOMER | Completed |