Permit Review Detail
Review Status: Active
Review Details: COMMERCIAL - NEW
Permit Number - T18CM01546
Review Name: COMMERCIAL - NEW
Review Status: Active
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/13/2018 | JPEELDA1 | FIRE | REVIEW | Approved | |
| 03/21/2018 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Verify the FFE for the warehouse; on sheet P1 it is 2584.20 but the civil plans show an elevation of 2585.2. Reference: Section 107.2.1, IBC 2012. 2. Revise detail 2/P1 to show the note regarding the T&P relief line. Reference: Section 107.2.1, IBC 2012. 3. Provide the architectural detail of the water heater platform referenced on sheet P3. Reference: Section 107.2.1, IBC 2012. 4. Provide an approved vacuum relief valve for the scheduled bottom-fed water heater that is located above the fixture outlets. Reference: Section 504.2, IPC 2012. 5. Change the size of the fixture drains for the water closets. Any fitting or connection in a drainage system that results in a reduction of the pipe area is prohibited. Reference: Section 706.2, IPC 2012. 6. Provide justification for the upstream cleanout shown in detail 201. Reference: Section 708.5, IPC 2012. 7. Assuming that each of the five downspouts on each side of the building drain equal roof areas, Table 1106.2, IPC 2012, a 5" diameter downspout (or its equivalent rectangular size per footnote b, Table 1106.2 (2), IPC 2012) is required. |
| 03/21/2018 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Show the supports for the discharge ducts for the evaporative coolers. Reference: Section 302.1, IMC 2012. 2. The energy use of the building appears to be about 1.5 Watts per square foot. Provide a COMcheck analysis for the building envelope. Reference: Section C101.5.2 and C401.2, IECC 2012. |
| 03/21/2018 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 03/27/2018 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. #1. Designate a branch circuit and panel for the Evap cooler maintenance receptacles. If they are sharing the pump circuit, please indicate this on the plans. #2. Provide for building steel bonding. 250.104 NEC Ref: 2012 IBC 107.2.1, 2011 NEC 408.4. |
| 04/03/2018 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | FROM: David Rivera PDSD Zoning Review Section PROJECT: T18CM01546 - New Building (Storage Use) Building Plan Review (1st Review) - Bilby Warehouse 2622 E Bilby Road TRANSMITTAL DATE: April 3, 2018 DUE DATE: April 6, 2018 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. COMMENT: Zoning has done a cursory review of the building plans. Prior to a more comprehensive review by zoning the Approval of the Revised DP is required. While the cursory review did yield an indication that the building plans are consistent with what has been proposed and drawn on the DP (that has been submitted for review) zoning cannot approve the building plans at this time. While the building footprint is consistent with the footprint on the DP as it relates to the zoning review purview (Building footprint, Height, square footage, site conditions etc.) zoning cannot approve the building plans until the Commercial Plans reviewer(s) have approved the building plans. 2. COMMENT: Zoning will review the building plans on the next submittal to assure consistency with the approved DP. If any changes are necessary to the building plans due to plan review comments that affect zoning requirements, the DP will have to be revised to reflect the changes. Once the DP is approved by all reviewers and the building plans are approved by the Commercial Plans reviewers zoning can approve the building plans. 3. COMMENT: Zoning will refer to the approved Development Package for reference and compliance. Include as reference a copy of the approved DP with the next submittal. If the DP has not been scanned at PDSD and not available for review as reference include a hard copy as "reference only" with the building plans. (Do not attach the DP or make them part of the building plans package.) If you have any questions about this transmittal, Contact David Rivera on Tuesday or Wednesday at (520) 837-4957 or by email David.Rivera@tucsonaz.gov or contact Steve Shields, (520) 837-4956 or Steve.Shields@tucsonaz.gov RESUBMITTAL OF THE FOLLOWING IS REQUIRED: building plans |
| 04/05/2018 | JOHN VAN WINKLE | ENGINEERING | REVIEW | Reqs Change | T18CM01546 1) A general review of the building plans was conducted and appears to be in compliance with first submittal of DP17-0237. Final approval of building plans requires that the open comments relating to the DP are addressed and the DP approved. An additional review of the building plans will be conducted once the DP has been approved. John Van Winkle, P.E. John.VanWinkle@tucsonaz.gov 520-837-5007 |
| 04/16/2018 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Show means of egress lighting on the reflected ceiling plan; label all components on plan. IBC 1006 GP 2. Provide an overall framing plan for the interior bathrooms; include span charts of roof framing members. IBC 107.2.1 GP 3. Indicate the ceiling heights of the bathrooms IBC 107.2.1 GP 4. Inficate where structural detail 211 occurs on the plans. IBC 1603.1 GP 5. Specify where the 1-hr. fire wall(s) are located on the floor plan; provide listed penetration details for all wall openings in fire wall. IBC 706. GP 6. Provide details of fire wall at the floor-roof assembly. IBC 706 GP 7. Provide the ER report#. for the wall fasteners to the concrete. IBC 107.2.1GP 8. Provide common path of egress travel measurements on on the plans. IBC TABLE 1014.3 GP 9. Provide measurements for the maximum travel distance using an access aisles along the wall line where no storage layout is indicated on the floor plan. IBC TABLE 1016.2 GP |
| 07/23/2018 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Approved |