Plan Review Detail
Review Status: Completed
Review Details: PIA - RESUBMITTAL
Plan Number - T17PI00028
Review Name: PIA - RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Completed | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
06/30/2017 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | |
07/07/2017 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Approved | |
07/18/2017 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Please let me know who cleared you during the development process for the Ash Trees this close to the cantinary lines. This is a privately owned development and as such will need to get an easement for the irrigation that are under public roadway. I will e-mail you the standard notes for planting in the ROW. Please add them to your plans. |
08/15/2017 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
08/15/2017 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Passed | NO RESPONSE FROM JFEMLING. APPROVED BY CSALTZMAN. - LI 8/15/17 |
08/15/2017 | LINZUNZA | PIA COORDINATOR | OUT TO CUSTOMER | Completed | |
08/15/2017 | CSALTZM1 | DOT ENGINEERING | REVIEW | Reqs Change | 1) Add Plan No. I-20017-010 to all sheets. 2) Sht 2 of 7: Detail 1 need dimension of column footing. |