Plan Number: T17PI00028
Parcel: Unknown

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T17PI00028
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/01/2017 GARY WITTWER DOT LANDSCAPE REVIEW Denied 1. There are 4 Ash trees on the north side of the building that may be in conflict with the Street Car cantinary lines. Trees can not grow into these lines.
2. There is another Ash tree at the NW corner of Linda and PDL Zanjeros that may be in conflict with those lines.
3. The parking area will be a public street. Private irrigation lines can not be under public roadway. I will e-mail criteria to Gary G.
3. NPPO statement?
05/05/2017 ZELIN CANCHOLA DOT TRAFFIC REVIEW Reqs Change May 5, 2017

SUBJECT: West End Station
PIA Plan T17PI00028, I-2017-017

PROJECT REVIEWER: Zelin Canchola,
TDOT Review Section

DOT Review Section has reviewed the PIA Plan for Traffic Engineering. The proposed striping and signing is acceptable. However the following changes/redlines is required for approval:

1. Page 6 of 7. Eliminate cross walk striping on Paseo De Los Zanjeros.

2. Page 6 0f 7. Add Street name signs to the proposed stop sign posts.


If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov
05/16/2017 LINZUNZA UTILITY CLEARANCES COT STREETS DIVISION Denied
05/16/2017 CSALTZM1 DOT ENGINEERING REVIEW Reqs Change 1) Sht. 1 of 7 -Cover Sheet - Note 7: The Geotechnical Report is not part of the construction documents. All information from the Geotechnical Report which is required to build the project shall be included in the plan set.
2) Sht. 1 of 7 -Cover Sheet - Add PIA No. T17PI00028
3) Add Plan No. I-2017-010 to all sheets
4) Sht. 1 of 7 -Cover Sheet- Location Map- Only include information a sub-contractor, supplier, surveyor world need to find the job site.
5) Project layout Map- This map has three primary functions.
A) Sheet number reference
B) Bidding tool -During the bid process the map is a tool for contractor. At a glance the contractor can determine if the project has the type of work his firm has the expertise in and do they want to bid on the work.
C) Research Tool - After the work has been completed the map is used as a research tool. Once again the person doing the research can determine from a glance if the issue they are researching was addressed in this set of plans without looking at the whole set.
6) Sht. 2 of 7- Cross Section Paseo De Los Zanjeros - Column footing is shown within the R/W. Move footing to outside of R/W.
7) Sht. 3 of 7- Need survey monument at intersection of Paseo de los Zanjeros and Linda Ave.
8) Sht. 4 of 7- Need curve table for all curves.
9) Sht. 5 of 7- Extend all sidewalk scuppers to curb openings.
10) Sht. 7 of 7 - Access Ramp Details - Use City of Tucson Access Ramps
11) Sht. 7 of 7 - Access Ramp Details calls out 2% in all directions - Please clarify.
12) Sht. 7 of 7 - Pavement Structure Detail
A) Show per cent compaction of subgrade
B) Show per cent compaction of A.B.C.
C) A.C. Pavement - Call out City of Tucson Mix #2 A) Show per cent compaction
05/16/2017 LPETERS2 DOT PERMITS & CODES REVIEW Approved
05/16/2017 CSALTZM1 DOT ENGINEERING REVIEW Reqs Change 1) Sht. 1 of 7 -Cover Sheet - Note 7: The Geotechnical Report is not part of the construction documents. All information from the Geotechnical Report which is required to build the project shall be included in the plan set.
2) Sht. 1 of 7 -Cover Sheet - Add PIA No. T17PI00028
3) Add Plan No. I-2017-010 to all sheets
4) Sht. 1 of 7 -Cover Sheet- Location Map- Only include information a sub-contractor, supplier, surveyor world need to find the job site.
5) Project layout Map- This map has three primary functions.
A) Sheet number reference
B) During the bid process the map is a tool for contractor. At a glance the contractor can determine if the project has the type of work his firm has the expertise in and do they want to bid on the work.
C) After the work has been completed the map is used as research tool. Once again the person doing the research can determine from a glance if the issue they are researching was addressed in this set of plans without looking at the whole set.
6) Sht. 2 of 7- Cross Section Paseo De Los Zanjeros - Column footing is shown within the R/W. Move footing to outside of R/W.
7) Sht. 3 of 7- Need survey monument at intersection of Paseo de los Zanjeros and Linda Ave.
8) Sht. 4 of 7- Need curve table for all curves.
9) Sht. 5 of 7- Extend all sidewalk scuppers to curb openings.
10) Sht. 7 of 7 - Access Ramp Details - Use City of Tucson Access Ramps
11) Sht. 7 of 7 - Access Ramp Details calls out 2% in all directions - Please clarify.
12) Sht. 7 of 7 - Pavement Structure Detail
A) Show per cent compaction of subgrade
B) Show per cent compaction of A.B.C.
C) A.C. Pavement - Call out City of Tucson Mix #2 A) Show per cent compaction
05/16/2017 LINZUNZA UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES PC WASTEWATER MGMT Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES QUEST COMMUNICATION Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES COX COMMUNICATION Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES EL PASO NATURAL GAS Denied
05/16/2017 LINZUNZA UTILITY CLEARANCES KINDER MORGAN ENERGY Denied
05/23/2017 JIM FEMLING DOT STREET MAINTENANCE REVIEW Reqs Change Extend the sidewalk scuppers on Linda and Congress all the way through the vertical curb.

No further comments - James Femling
05/23/2017 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
05/23/2017 LINZUNZA PIA COORDINATOR OUT TO CUSTOMER Completed