Plan Number: T17PI00024
Parcel: Unknown

Address:
460 N FREEWAY

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T17PI00024
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/29/2017 LINZUNZA UTILITY CLEARANCES COT STREETS DIVISION Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES PC WASTEWATER MGMT Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES QUEST COMMUNICATION Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES COX COMMUNICATION Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES EL PASO NATURAL GAS Denied
03/29/2017 LINZUNZA UTILITY CLEARANCES KINDER MORGAN ENERGY Denied
04/24/2017 GARY WITTWER DOT LANDSCAPE REVIEW Approved
04/24/2017 ZELIN CANCHOLA DOT TRAFFIC REVIEW Reqs Change April 24, 2017

SUBJECT: U-Haul of El Presidio
PIA Plan T17PI00024, I-2017-007

PROJECT REVIEWER: Zelin Canchola,
TDOT Review Section

DOT Review Section has reviewed the PIA Plan. The following changes/redlines are required for approval:

Page 5 of 6
6. Eliminate striping. Striping not required.
7. Eliminate "only" sign. Replace with "one way" R6-1(R) at frontage road. Eliminate "only" sign at St Mary's Road. No additional sign required.
8. Eliminate one "not a thru street" at frontage Road. (north corner)
9. Eliminate Stop sign and stop bar at entrance from Hotel.

If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov
04/24/2017 ZELIN CANCHOLA DOT ENGINEERING REVIEW Reqs Change April 24, 2017

SUBJECT: U-Haul of El Presidio
PIA Plan T17PI00024, I-2017-007

PROJECT REVIEWER: Zelin Canchola,
TDOT Review Section

DOT Review Section has reviewed the PIA Plan. The following changes/redlines are required for approval:

1. Include job number, plan number I-2017-007, activity number T17PI00024
2. Provide basis of bearing, and elevation (reference cot field book and page) on cover sheet.
3. Eliminate approval line for Pima County on cover sheet
4. The profile portion shall show existing grades at both right-of-way lines and centerline alignment. The new grades shall be shown at centerline and both top of curb and gutter, or at edge of pavement if no curb is to be constructed. All three control lines will show elevations, stationing, percent of grade and all necessary related profiles pertaining to existing sanitary sewers, storm sewers.
5. Sheet 3 of 6 Eliminate 5 foot concrete sidewalk at Driveway (where light pole is located) asphalt driveway is suffice. Ensure 2% max slope for ADA.


Page 5 of 6
6. Eliminate striping. Striping not required.
7. Eliminate "only" sign. Replace with "one way" R6-1(R) at frontage road. Eliminate "only" sign at St Mary's Road. No additional sign required.
8. Eliminate one "not a thru street" at frontage Road. (north corner)
9. Eliminate Stop sign and stop bar at entrance from Hotel.

If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov
05/04/2017 LPETERS2 DOT PERMITS & CODES REVIEW Denied I have reviewed this plan and have the following comments:

1. In some areas you have called to match existing curb and gutter. Other streets seem to have vertical curb existing and you have called out curb and gutter. Why woudl you call out curb and gutter whee we are not matching in kind?
2.Sheet 1 - note 1 - This calls out the 2015 PAG Standard Specifications and Detail but in the plans there is a sheet of MAG specs. Is there not a coresponding PAG spec?

No further commments

Lance Peterson
(520) 837-6777
05/16/2017 JIM FEMLING DOT STREET MAINTENANCE REVIEW Passed NO COMMENTS REC'D. PASSED LI
05/16/2017 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
05/16/2017 LINZUNZA PIA COORDINATOR OUT TO CUSTOMER Completed