Permit Number: T17CM09408
Parcel: 11941043A

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T17CM09408
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/16/2019 KEN VAN KARSEN BUILDING-RESIDENTIAL REVIEW Passed
05/20/2019 LOREN MAKUS ENGINEERING REVIEW Reqs Change 1. All building components below the regulatory flood elevation (RFE) must meet the requirements of "Flood Damage-Resistant Materials Requirements" FEMA Technical Bulletin 2, August 2008 or later. Please provide documentation that all materials used below the regulatory flood elevation meet the requirements of the Technical Bulletin.
2. Clearly show on all relevant plan sheets the required flood venting for the enclosure below the RFE. Provide documentation that the flood venting meets the requirements of FEMA Technical Bulletin 1.
3. Show elevation of the gas meter to above the RFE or provide a letter from SWGas certifying its meters are suitable for potentially flooded situations.
4. Show how use of the lowest floor will be restricted to parking and storage. Provide recorded document or other equivalent mechanism to ensure continued compliance with this requirement.

Final Status

Task End Date Reviewer's Name Type of Review Description
05/21/2019 QJONES1 APPROVAL SHELF Completed
05/21/2019 QJONES1 OUT TO CUSTOMER Completed
05/21/2019 QJONES1 REJECT SHELF Completed