Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - TI ALL
Permit Number - T17CM08496
Review Name: RESUBMITTAL - TI ALL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/10/2018 | MARTIN BROWN | FIRE | REVIEW | Approved | |
01/17/2018 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet 0.1; Codes: Please add the 2009 ICC/ANSI A117.1 accessibility code to this list. 2. Sheet 1.1; Detail 3: A note indicates "Existing Building FFE". What existing building is this a reference to? Please verify. 3. General: Please provide written responses to all review comments. |
01/24/2018 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. If the vehicle engines are operated for more than the time required to enter or leave the repair bays, provide a source capture exhaust system that connects directly to the vehicle exhaust system. Reference: Section 502.14, IMC 2012. 2. Provide for draining of the evaporative coolers. Reference: Section 928.1 (1), IMC 2012. |
01/24/2018 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Correct the orientation of the north arrow for the mechanical & plumbing plan. Reference: Section 107.2.1, IBC 2012. 2. Verify that all of the vents (except for vents serving interceptors located outdoors) rise vertically to at least 6" above the flood rims of the fixtures they protect prior to running horizontally. Reference: Section 905.4, IPC 2012. 3. Provide a vent for the combination waste and vent system in the existing truck service bay. Reference: Section 915.2.2, IPC 2012. |
01/24/2018 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | 1. Verify the water pressure available to the site. Per Tucson Water, the water pressure range for this address will be approximately 84.8 to 91.8 PSI. 2. Revise the site plan (sheet 01) to show the location of the existing water meter and backflow preventer. Determine the total water demand served by this water meter. Reference: Section 107.2.1, IBC 2012. |
02/02/2018 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
02/05/2018 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Principle Planner PROJECT: Holms Tuttle Ford T17CM08495 & T17CM08496 Building Plan (2nd Review) TRANSMITTAL DATE: February 5, 2018 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. The development package sheets provided in the building set either need to be the approved and signed plans, marked as "FOR REFERENCE ONLY" or removed from the building set. 3. Until the above comments have been addressed and all other PDSD review agencies have approved the building plans zoning cannot approve. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
02/08/2018 | BLARSON1 | OUT TO CUSTOMER | Completed |