10/05/2017 | KELLY LEE | ZONING | REVIEW | Approved | |
10/05/2017 | KLEE1 | ENGINEERING | REVIEW | Passed | |
10/06/2017 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
10/06/2017 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Reprint the registrant's seal so that it is legible. 2. Revise the sequence of operation for the restroom exhaust fan so that all of the air supplied to the restrooms will be exhausted (i.e. all of the air supplied to each restroom is to be exhausted during the hours of operation even if the lights are off). Reference: Section 403.2.1 (4), IMC 2012. |
10/06/2017 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Sheet T1; Code Data (Governing Codes): Please add the 2009 ICC/ANSI A117.1 accessibility code to this list. 2. Sheet T1; Minimum Plumbing Facilities: Reference is made to Table 422.1. Please revise the reference for the 2012 IBC. 3. Sheet T1: Is this building sprinklered? Please verify and indicate on the drawings. 4. Sheet CS; Code Compliance Plan: Per the IBC Section 2902.3.1, the toilet facility shall not pass through kitchens, storage rooms, or closets. Although this room is designated as a work room, storage appears to be the primary use. Please verify. 5. Sheet CS; Restroom Elevation 2: Please locate the rear wall horizontal grab bar per the ICC/ANSI Figure 604.5.2. 6. Sheet A5; Water Heater Platform Framing Details 1 and 1A: It appears the platform structure supporting the hot water heater are metal studs cantilevered from a metal stud wall. Please provide structural calculations for the platform joists, the metal stud wall supporting this platform, and the connection of the joists to the wall. 7. General: Please provide written responses to all review comments. |
10/06/2017 | ROBERT SHERRY | WATER | REVIEW | Completed | |
10/06/2017 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Reprint the registrant's seal so that it is legible. 2. Revise the water distribution system design criteria to provide a pressure drop for the existing reduced pressure zone assembly. Reference: Section 604.1, IPC 2012. 3. Revise the operation of the lavatory faucet to operate for a minimum time of 10-seconds. Reference: Section 606.4, ICC/ANSI A117.1-09. 4. Clarify the specification of the thermostatic mixing valve. The model number quoted is made by Watts, not Zurn. Provide tempered water for the public restroom lavatory using a device conforming to ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2012. 5. Provide separate indirect waste pipes for each compartment of the 3-compartment sink to protect against cross-contamination or fouling. Reference: Sections 801.2 and 802.1.8, IPC 2012. |
10/06/2017 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
10/09/2017 | MARTIN BROWN | FIRE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/26/2017 | QJONES1 | APPROVAL SHELF | Completed |
10/26/2017 | QJONES1 | OUT TO CUSTOMER | Completed |