Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T17CM06093
Parcel: 14121025C

Review Status: Completed

Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG

Permit Number - T17CM06093
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/22/2017 MARTIN BROWN FIRE REVIEW Reqs Change Provide site plan indicating location of shade structures to property lines.
08/31/2017 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Principle Planner

PROJECT: Old Vail Storage - Covered Parking Structures
T17CM06093
Building Plan (1st Review)

TRANSMITTAL DATE: August 31, 2017

1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning has reviewed the building plans for the covered parking and it appears that the plans match what is shown on DP17-0153 but until DP17-0153 is approved Zoning cannot approve the building plans.

3. Until the above comments have been addressed and all other PDSD review agencies have approved the building plans zoning cannot approve.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
09/12/2017 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. General: Please provide a full size site plan for this project. Indicate the location of all structures on the plan, including the dimensions of the structures from each other and from the property lines.
2. General: Please provide a code analysis on a sheet, indicating each structure type, square footage, construction type, and occupancy classification. Include an allowable square footage determination per the IBC Table 503.
3. General: The Special Inspection Certificate must indicate the name of the individual performing the inspection for each category (under 'Special Inspector').
4. General: Please provide written responses to all review comments.
09/12/2017 LOREN MAKUS ENGINEERING REVIEW Reqs Change DP must be approved first.

Final Status

Task End Date Reviewer's Name Type of Review Description
11/22/2017 QJONES1 APPROVAL SHELF Completed
11/22/2017 QJONES1 OUT TO CUSTOMER Completed
11/22/2017 QJONES1 REJECT SHELF Completed