Plan Review Detail
Review Status: Completed
Review Details: PIA - SUBMITTAL
Plan Number - T16PI00019
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | |
10/20/2016 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | |
11/08/2016 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Reqs Change | November 8, 2016 ACTIVITY NUMBER: T16PI00019 PROJECT NAME: Valencia Haedly Site PROJECT ADDRESS: 1955 W Valencia Rd PROJECT REVIEWER: Zelin Canchola TDOT Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan therefore a revised plan is required for re-submittal. The following items must be revised or added to the plan. Include a response letter with the next submittal that states how all comments have been addressed. Sheet 6 of 9: 1. As noted on plan, revise number of signs on sign summary. 2. On signing notes change phone number of Street Maintenance to 520 791 3191 on note 9. On note 11 eliminate reference to Pima County, should be City of Tucson. Sheet 7 of 9: 1. Add right turn signs as noted on plan. New R3-5R, and right lane R3-5fp plaque typical to right turn lanes. 2. Add new begin right turn lane yield to bikes sign. 3. Add new stop signs, and stop legends at driveways. Stop signs should be placed outside of right of way. 4. Right turn bay shows 3 arrow legends. Two are required. Sheet 8 of 9: 1. Add new right turn only sign at northern driveway. If you have any questions, I can be reached at 520 837 6659 or zelin.canchola@tucsonaz.gov |
11/14/2016 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | The COT has existing landscape and irrigation along the shoulder and in the median. Please address providing sleeves for the existing system under new paved entrances and in the median reduction. You will need to mitigate tree removal 2 new tree for each one removed. Contact Streets to fine the location and extent of irrigation system. There appears to be a private irrigation crossing on the side street off Headly. If this is under a publis roadway you will need to follow the City's new Detail. Please call me for that information. 837-6618 |
11/14/2016 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Approv-Cond | November 10, 2016 SUBJECT: Valencia/Headley Site Offsite Improvements PROJECT REVIEWER: Richard Leigh, TDOT Engineering Review RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and recommends a conditional approval. The following comments need to be addressed and plans revised prior to final approval. 1. Include the plan number "U-2016-016" in the title block of each sheet. 2. Include the PIA activity number "T16PI00019" on cover sheet. 3. Provide construction joint details for PCCP longitudinal joints, PCCP to Curb and PCCP to Half Barrier. If you have any questions, I can be reached at 837-6647 or emailed at Richard.Leigh@tucsonaz.gov. Traffic Engineering Comment. Construction Keynotes 1, 2, and 3 Replace all references to "Type Q signal heads" with "4-section signal head populated Red Arrow, Yellow Arrow, Flashing Yellow Arrow, Green Arrow, in accordance with the 2009 MUTCD figure 4D-12". Paul Burton, TSOS Electronics Technician Supervisor City of Tucson Department of Transportation 520.791.3191 |
11/15/2016 | LPETERS2 | DOT PERMITS & CODES | REVIEW | Denied | I have reveiwed this plan and have the following comments: 1. Sheet 2 of 9 - Right Lane Detail - You have called out a 1" AR-ACFC over 8" of PCCP. Is thisjsut matching existing? 2. Sheet 4 of 9 - Median in Plan View - The ends of this median modification appear to be approximately 20 feet of just vertical curb? This seems to be a traffic hazard. No further comments at this time. Lance Peterson, P.E. (520) 837-6777 |
11/15/2016 | JIM FEMLING | DOT STREET MAINTENANCE | REVIEW | Approv-Cond | Add a comment that all landscape and irrigation disturbed will have to be replaced by the contractor. If you have any questions I may be reached at James.Femling@tucsonaz.gov |
11/16/2016 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Reqs Change | 1. Relocated street light poles at approx. 18+60 and 20+40 are being relocated further back from curb and closer to existing TEP power lines. Verify installation of poles will not be inconflict with TEP requirements for clearance and acceptance. 2. New conduit and conductors shall be installed behind curb in any area that the roadway median is moved back. No conduit shall be in roadway, except for street crossings or driveway cuts. 3. Traffic signal plans to reflect 4 section heads for left turn movements, not 5 section 'Q' heads. |
11/18/2016 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |
11/18/2016 | LINZUNZA | PIA COORDINATOR | OUT TO CUSTOMER | Completed |