Plan Review Detail
Review Status: Completed
Review Details: PIA - RESUBMITTAL
Plan Number - T16PI00014
Review Name: PIA - RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/22/2016 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approved | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | |
| 11/22/2016 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | |
| 11/22/2016 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Passed | |
| 11/22/2016 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
| 11/22/2016 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | |
| 12/20/2016 | LPETERS2 | DOT PERMITS & CODES | REVIEW | Approved | |
| 12/22/2016 | CSALTZM1 | DOT ENGINEERING | REVIEW | Reqs Change | 1.Need Plan number. 2.Need to show PIA number on sht. 1 top center below Title 3.Key note 1 calls out "2' trim, tack and join new to existing pavement. Add; the word" pavement" after the work new 4.Sht. 2 of 4 Plan view call out Sta. where new pavement begins. 5.Sht. 2 of 4 Plan view call out Sta. where new pavement ends. Note: 1) Approximate stations are used as reference in the comments - Engineer will calculate exact stations, outs and elevations. 2) None of the dimensions shown locate the edge of new pavement from the construction center line along Manitoba Ave. 6.Sht. 2 of 4 Plan -Shade new asphalt on plan view sta. ~1+50 to ~7+50 on Manitoba. 7.Sht. 3 of 4 Plan -Shade new asphalt on plan view sta. ~1+40 to Sta. ~2+75 Escalante Rd. (2' trim tack join) 8.Sht. 2 of 4 Profile there is a note which calls out 7+45.47 End new pavement. Need a note calling out Begin new pavement. 9.Sht. 3 of 4 Neither Plan or Profile call out where to begin or end new pavement. 10.Sht. 2 of 4 Sidewalk Scupper: Plan -need note calling out Sta. and out. Profile - show sta. and elevation. FYI: Profile- the reference elevation are shown to the thousands (2755) place. The call out for the spot elevations only need to be called out to tenth place (55.45 not 2755.45). 11.Sht. 2 of 4 Need to show B.M.'s for construction. One at approx. Sta. 2+00 and another at the other end of Manitoba Sta. ~7+00. 12.Sht. 2 of 4 Horizontal curve table - curve C1 need to show tangent A.Need to call out BC and EC with Sta. and outs for C1 in the plan view. B.Profile views need to call out BC and EC for C1 with gutter and top of curb grades. 13.Sht. 2 of 4 Profile show new curb and gutter as solid lines- only existing features should be shown as dash lines. 14.Sht. 2 of 4 Profile Grades of 2.0% and 3.1% are shown. The delta of the two grades is greater than 1- need a vertical curve. 15.Sht. 2 of 4 Profile between Sta. 1+48 to Sta. 5+22 show three slopes and only one grade brake, (1.0%, 2.0% and 3.1% grades). Need to call out second grade brake. 16.Key Note 2 change to read: New concrete vertical curb (TYP.) per PC/COT SD 209, match existing. 17.Sht. 3 of 4Show gutter grade between Sta. 1+21 and Sta. 2+32. 18.Sht. 3 of 4 Plan view call out Sta. where pavement begins on Escalante Rd. 19.Sht. 3 of 4 Plan view shade new 2' asphalt pavement. 20. Sht. 3 of 4 Plan view shows a dimension of 25.2' from island to curb. What is the dimension form the construction center line to the curb? 21.Sht. 3 of 4 plan view shows a dimension of 25.8' for the width of the driveway. Detail D on Sht.4 of 4 shows a dimension of 16' for the width. Which dimension??? 22.Sht. 4 of 4 Remove Curb access Ramp Detail with cross outs and corrections and re-draw as new detail. 23.All ADA Access Details need to be current per City of Tucson standard details 2016 book. |
| 12/22/2016 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 12/22/2016 | LINZUNZA | PIA COORDINATOR | OUT TO CUSTOMER | Completed |