| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | |
| 07/26/2016 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Passed | NO ELECTRICAL |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | |
| 07/26/2016 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | |
| 08/10/2016 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | There ae two small median island Fremming. Will they be landscaped? Would prefer to see them concreted in. |
| 08/11/2016 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Reqs Change | August 11, 2016 ACTIVITY NUMBER: T16PI00011 PROJECT NAME: Elementary Place PROJECT ADDRESS: 7500 E Pima St PROJECT REVIEWER: Zelin Canchola TDOT Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan therefore a revised plan is required for re-submittal. The following items must be revised or added to the plan. Include a response letter with the next submittal that states how all comments have been addressed. Sheet 2 of 9: 1. Revise note 3 from Striping notes to reflect this project. Sheet 5 and 6 of 9: 1. Add no parking fire lane signs to cul de sacs Add speed hump detail. If you have any questions, I can be reached at 520 837 6659 or zelin.canchola@tucsonaz.gov |
| 08/24/2016 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | August 19, 2016 SUBJECT: Paving Plans for Elementary Place, Lots 1-51 PROJECT REVIEWER: Richard Leigh, TDOT, TDOT Eng. Review RESUBMITTAL REQUIRED: TDOT Permit Review Section has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments and return redlined drawings with subsequent submittal. 1. Include the plan number "I-2016-009" in the title block of each sheet. 2. Include the PIA activity number "T16PI00011" on cover sheet. 3. Sheet 3, Detail A & B: Indicate the final surface treatment of the Median Islands. 4. Sheet 5: Verify that the proposed grades at the intersection of Chalkboard Court & Fremming Ave and Bookmark Pl & Fremming Ave will prevent stormwater flows from ponding in the intersections. 5. Sheet 5 & 6: Indicate the placement of Barricade railing along the back side of proposed sidewalk scuppers. 6. Sheet 7: Indicate that the relocated speed hump is placed per PCDOT & TDOT Traffic Engineering Division Pavement Marking Standards 5-18.1. 7. Sheet 8, Section 1: The minimum roadway cross slope for a roadway with a longitudinal grade greater that 0.5% is 2%. Verify that roadway grades and slopes comply with COT Technical Standards Manual Section 10-0.4.5. 8. Please Refer to redline plans for additional comments and comment details. If you have any questions, I can be reached at 837-6647 or emailed at Richard.Leigh@tucsonaz.gov. |
| 08/25/2016 | LINZUNZA | DOT PERMITS & CODES | REVIEW | Reqs Change | 1. Sheet 2 - Note 6 - Asphalt Concrete should conform to City of Tucson, TDOT Mix#2. This is a new mix that is different from what is called out in section 406 of the PC/COT SS. 2. Sheet 4 - Keynote 8 - This note calls for 5 foot wide sidewalks. Detail on sheet 9 shows the sidewalk along Pima as 6 foot wide. 3. Sheet 7 - Keynote 8 - This note calls for 5 foot wide sidewalk. Detail on sheet 9 shows sidewalk along Fremming as 6 foot wide. |
| 08/26/2016 | JIM FEMLING | DOT STREET MAINTENANCE | REVIEW | Approved | |
| 08/26/2016 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |