04/21/2016 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
04/21/2016 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | |
05/05/2016 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | No private irrigation lines under public roadway. Please check with the Engineer for the ROW line at the SW corner of the project. The PIA is indicating that the public roadway will extend into the property. Please relocate your irrigatiion crossing outside the ROW and under the private street |
05/16/2016 | ERNIE ENCINAS | DOT_ELEC | REVIEW | Denied | Date: May 16, 2016 Project Name: Offsite Improvement Plan for Irvington Road & Calle Santa Cruz Plan#: U-2016-008 Activity Number: T16PI00006 Project Reviewer: Paul Burton, Streets & Traffic Maint. Division, Electric Shop Comments: Sheet 15 of 36 Add Note - All existing conductors shall be removed and salvaged to City. Install new conductors per conduit schedule. Pole E: add luminaire mast arm and luminaire. Pole F: Remove existing. Replace with Type II ped pole and button. Northwest corner: Add "G" pole with 20' mast arm. Install luminaire. Relocate turn signal; from pole (F) to this new pole designated ( P) on type V mount. Install Ped button and ped head on type XI mount Northeast corner: Add "G" pole with 20" mast arm. Install luminaire. Install "Q" head from pole (L) on type V mount. Install Ped button and ped head on type XI mount. Pole (L) Remove left turn indication. Replace side mount with type V mount. Sheet 16 of 36 Signal heads referred to as "modified F" head are actually "R" heads; ADOT T.S. 8-0 Replace all references to "internally illuminated street name signs" with "flagpole-mounted Metro signs". Replace references to Peek video detection cameras with Autoscope Encore video detection camera. Preempt sensors shall be Tomar model 2091-ST sensors. Ped push buttons shall be 2" ADA compliant piezio-discharge, non-movable type. Contractor to verify luminaire type before purchasing equipment. All luminaires shall be compliant with luminaire upgrade project and shall have ROAM node and 7-pin photocell sockets. Contact Ernie Encinas (520) 837-6782 for current specifications. Replace pole (F) with type II ped pole on existing foundation. Add poles (P) and (Q). Correct indicated mount types. Page 17 of 36 Correct conduit and conductor schedule Page 18 of 36 Replace reference to IISNS with "Flagpole mounted Metro signs". Page 19 of 36 Add Poles (Q) and (R) where shown Pole (P): "G" pole with 20' mast arm, ped push button, man/hand indication and type XI mount. Replace pole (F) with type II Ped Pole & ped push button. Pole (E) : Add 20' luminaire mast arm, luminaire, relocate existing video detection camera. Replace "Q" head with "R" head. Pole (D): Add "R" head and type V mount. Pole (N): Remove "R" head abd areplace mount with type V. Add man/hand indications Pole (R): "G" pole with 20' mast arm, luminaire, ped oush button, "R" head and "F" Head on type 7 mount. Sheet 20 of 36 Correct drawings as shown. All existing conductors to be removed and salvaged to City. Install new conductors per conductor schedule. Sheet 21 of 36: correct conductor and conduit schedule. If you have any questions, I can be reached at Paul.Burton@tucsonaz.gov |
05/16/2016 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Reqs Change | May 16, 2016 ACTIVITY NUMBER: T16PI00006 PROJECT NAME: Irvington @I-19 commercial Center PROJECT ADDRESS: 1150 W Irvington Road PROJECT REVIEWER: Zelin Canchola TDOT Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan therefore a revised plan is required for re-submittal. The following items must be revised or added to the plan. Include a response letter with the next submittal that states how all comments have been addressed. Sheet 24 of 36: 1. Add west bound Bike lane to Calle Santa Cruz intersection Sheet 25 of36 2. Add/Continue Bike lane If you have any questions, I can be reached at 520 837 6659 or zelin.canchola@tucsonaz.gov |
05/17/2016 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |
05/17/2016 | JIM FEMLING | DOT STREET MAINTENANCE | REVIEW | Approved | |
05/17/2016 | LINZUNZA | DOT PERMITS & CODES | REVIEW | Denied | May 17, 2016 SUBJECT: Offsite Improvement Plan for Irvington & I-19 Commercial Center U-2016-008/T16PI00006 PROJECT REVIEWER: Tom Adkins, TDOT Construction Inspection Review RESUBMITTAL REQUIRED: TDOT Construction Inspection Review has reviewed the subject PIA paving plan and does not recommend approval at this time. The following comments need to be addressed and plans revised prior to resubmittal. Please include a response letter addressing the following comments and return redlined drawings with subsequent submittal. 1. Page 1 of 36, note 17: Paving and grading notes change "SHOULD" to "SHALL". 2. Page 2 of 36, Detail A: Change pavement section to 5" #1 & 3" #2. 3. Page 3 of 36: Elevation and plan view stationing do not match. 4. Page 4 of 36: Elevation and plan view stationing do not match. 5. Pages 5 & 6 of 36: Change cross sections of roadways in details to reflect new Detail A on page 2 of 36. If you have any questions, I can be reached at 791-5100 or Tom.Adkins@tucsonaz.gov. |
05/17/2016 | CSALTZM1 | DOT ENGINEERING | REVIEW | Reqs Change | 1) Remove Curb & Gutter - use City of Tucson Curb- COT Standard 209 Concrete Vertical Curb (8" Reveal) Type 2 2) Remove Valley gutters at approx.. Sta 25+75 and Sta 29+50 north side of Irvington Rd. Replace with vertical curves. 3) Remove key note: No. 15 New Concrete Valley Gutter 4) Sta 27+42 Lt. 66' Irvington Rd. New Bus Shelter Pad(Relocation). Need detail of pad and location dimensions. 5) Sta 25+38 Lt. 48' to Sta 28=83 Lt. 62' new Bus Pullout- provide detail and concrete structural section for bus pullout (sample City of Tucson Plan U-2009-034) 6) Sheet 5: Cross Section, (Irvington Rd.) Sta 24+45.59 provide detail of Catch Basin 7) Box Culvert Sta 12+02 Calle Santa Cruz: A) Provide Sidewalk and Handrail both sides of roadway B) Use an ADOT standard box culvert for Box C) Sheet 29 of 36: Irvington I-19 S.W. Culvert Plan - use standard section call outs. 8) Clarify why sidewalk was dropped from Sta 30+00 to Sta 36+00 north side of Irvington Rd. Standard practice is to install sidewalk along 9) Provide ADOT review of project within the ADOT Control Access Area. |
05/17/2016 | LINZUNZA | PIA COORDINATOR | OUT TO CUSTOMER | Completed |