Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T16CM08804
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/11/2017 | GERRY KOZIOL | WWM | REVIEW | Reqs Change | The following are needed for Sewer Connection Fee Application Approval: A drawing showing the location and method of connection to the public sewer needs to be submitted with the COT building drawing set (site drawing P1 shows connecting to a 27” public sewer) *If connecting to the existing 8” private sewer on the adjacent property (Target), a private joint sewer use agreement and a private sewer easement will be required Need to clarify plumbing drawing P1 – Key Notes indicate a 2” water meter and Water Calculations indicate an 1-1/2” water meter Thank you, Gerry *The type III sewer capacity has been submitted 1/4/17 and currently is under PCRWRD review(P17WC00001) *Does not include PCRWRD review for future grease interceptor |
| 12/30/2016 | STEVE SHIELDS | ZONING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 02/14/2017 | FERNE RODRIGUEZ | OUT TO CUSTOMER | Completed |