Permit Number: T16CM07450
Parcel: 12101103E

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T16CM07450
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/03/2016 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Revise the sequence of operation for the restroom exhaust fan so that all of the air supplied to the restrooms will be exhausted (i.e. all of the air supplied to each restroom is to be exhausted during the hours of operation even if the lights are off). Reference: Section 403.2.1 (4), IMC 2012.
2. Revise the mechanical design as required to avoid using an egress corridor as a return air duct (see HP-1, hall 4). Reference: Section 601.2, IMC 2012.
3. How is the 100 CFM supplied to Hall 7 returned to HP-4?
4. Update the "2012 IECC Compliance Notes" on sheet M1.0 using the correct section numbers (e.g. there is no 403.5 in the 2012 IECC and the other section numbers are incorrect). Reference: Section 107.2.1, IBC 2012.
10/03/2016 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide structural calculations for mounting the water heater on a cantilevered shelf to show that the wall can safely support the water heater. Reference: Section 301.2, IPC 2012.
2. Specify that the automatic lavatory faucets will dispense a maximum of 0.25 gallons per metering cycle and that the automatic faucets will operate for a minimum time of 10-seconds. Reference: Section 416.6, IPC 2012, as amended by the City of Tucson and Section 606.4, ICC/ANSI A117.1-03.
3. The specification for the hand sinks on sheet P0.1 calls for a 105 GPM aerator. The maximum flow rates for plumbing fixtures shall be consistent with ARS Title 45, Chapter 1, Article 12. See text at: (http://www.azleg.state.az.us/ArizonaRevisedStatutes.asp).
4. Revise detail 2/P3.0 to state that the thermostatic mixing valves are to be provided for the lavatory faucets. Reference: Section 607.1.2, IPC 2012.
5. Detail 1/P3.0 calls for the T&P relief to terminate to the exterior of the building; show how this is to be done. Reference: Section 504.6, IPC 2012.
6. Provide cleanouts for all horizontal drains; the cleanouts shall be sized per Section 708.7, IPC 2012 (i.e. 3" drains require 3" cleanouts, 4" drains require 4" cleanouts). Reference: Sections 708.3.1 and 708.5, IPC 2012.
7. Clarify the connection of the hot water return piping to the cold water supply to the water heater and the configuration of the recirculating pump and valves. as shown in detail 1/P3.0.
8. Hot water and hot water return piping shall be insulated even if they are not being installed in a return air plenum (see plumbing specifications on sheet P0.1). Reference: Section 404.5, IECC 2012.
9. Update the "2012 IECC Compliance Notes" on sheet P0.1: Chapter 5 in the 2012 IECC is Referenced Standards.