Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/06/2016 | CPIERCE1 | ZONING | REVIEW | Approved | Approval done by Patricia |
06/06/2016 | PIMA COUNTY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
06/06/2016 | PIMA COUNTY | ELECTRICAL-COMMERCIAL | REVIEW | Completed | |
06/06/2016 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
06/06/2016 | PIMA COUNTY | BUILDING-COMMERCIAL | REVIEW | Reqs Change | PLANS REVIEW COMMENTS - T16CM04141 New foundations, steel framing, doors and frames, EIFS exterior wall system, roofing system, and underground plumbing only. Reviewer: Chris Anderson SHEET s2.0: 1. Plan 1/S1.0 should be labeled "roof framing plan". Detail markers 202 and 203 appear to be reversed. SHEET as8.0 1. Detail 2/as8.0 (101/s3.0) indicates a new exterior wall set on an existing concrete slab and the only barrier to prevent water from entering the building is a sealed joint between bottom of EIFS and slab. Because of this the moisture barrier behind the insulation board has no way of draining. Most EIFS systems require a 2" separation between bottom of EIFS and paved areas; and although this new addition could be located far enough under the existing walkway that no driven rain will reach it, perhaps not - especially if the existing slab is sloped such that ponding could occur in this location. Use detail 6/as8.0 (102/s3.0) at all new exterior EIFS walls. 2. There are many existing large exposed pipes running through this area under the existing walkway. Will any penetrate the new EIFS exterior wall system? Is so, provide penetration detail(s). |
06/06/2016 | PIMA COUNTY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | PLANS REVIEW COMMENTS - T16CM04141 New foundations, steel framing, doors and frames, EIFS exterior wall system, roofing system, and underground plumbing only. Reviewer: Chris Anderson SHEET p1.1: 1. Show drain pipes and sizes for new shower at the Home locker rooms. 2. What are the two clothes washers draining to? 3. Show drain pipes and sizes for the new shower at the UA restroom. 4. Keynote 4 says "New soil line, sizes to be shown in contract documents." These are contract documents for underground plumbing. Please clarify intent. 5. Provide plumbing materials specification. |
06/08/2016 | CPIERCE1 | WATER | REVIEW | Reqs Change | Provide the size of the water meter(s) serving this building, the size of the backflow preventer(s) associated with the water meter(s), and the total water demand served by the water meter(s). Reference: Section 107.2.1, IBC 2012. |
06/08/2016 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Reqs Change | Provide a site plan showing location of work reletive to overall site and a north arrow. Please also add a note indicating that location of offsite stormwater discharges will not change |