Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESIDENTIAL - BLDG/WWM
Permit Number - T16CM03432
Review Name: RESIDENTIAL - BLDG/WWM
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/19/2016 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 06/07/2016 | KEN VAN KARSEN | BUILDING-RESIDENTIAL | REVIEW | Reqs Change | T16CM03432 PLAN REVIEW COMMENTS Plan review for the above referenced structure has been completed. This letter reflects comments to be addressed. In order to facilitate a shorter back check time, please provide two sets of updated plans and calculations with a written response to each of the notated items indicating action taken. Do not cloud the changes made for comment revisions. SCOPE OF REVIEW: The scope of this plan review covers architectural, plumbing, mechanical, energy conservation and electrical. All code references are to the 2012 International Residential Code and 2012 International Energy Conservation Code. All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. FLOOR PLANS: 1. Show the location of a minimum 22" x 30" attic access. Attic access is required for areas exceeding 30 SQ FT with a minimum of 30" of headroom and located in a hallway or readily accessible space, R807.1. SECTIONS - DETAILS: 1. An unvented roof assembly requires an air-impermeable rigid insulation material with a minimum R-5 value applied correctly to either side of the roof sheathing (closed cell spray or rigid board tight to the roof sheathing), R806.5. This condensation control provision is necessary for code compliance, and may be a single layer of air-impermeable insulation, or layered with batt insulation for achieving the total required roof R-value. This applies to both Detail 1 & 2 (section 2 & 1) as currently shown. 2. Clarify the placement of ceiling/roof insulation for determining the need for attic ventilation, R806. If a vented roof assembly method will be utilized then show the ceiling insulation at the top of the ceiling, or if the location on Detail 2 (section 1) is correct then remove the vent calculation. 3. Show the interior load bearing wall foundation on Detail 2 (section 1) sheet A3, R106.1.1. If you have any questions please contact: Ken Van Karsen (520) 837-4912 City of Tucson Residential Plan Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/16/2016 | KROBLES1 | OUT TO CUSTOMER | Completed |