Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T16CM03297
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/06/2016 | MARTIN BROWN | FIRE | REVIEW | Reqs Change | The height of the building would indicate future use includes high piled storage. Please review chapter 32 and specifically table 3206.2 of the 2012 International Fire Code and determine which general fire protection and life safety requirements are applicable to this structure. Designate on plans. Be aware future use will be limited to life safety and fire protection components installed. |
05/18/2016 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | 1. Verify the available water pressure for this site with Tucson Water. Use the minimum daily service pressure for the water pressure calculations. Reference: Section A1.1, UPC 2012. 2. Specify the manufacturer and model of the reduced pressure backflow preventer that has a pressure drop of 8.5 PSI. Reference: Section 107.2.1, IBC 2012. |
05/23/2016 | PIMA COUNTY | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | SHEET E1.0 1. Add 9 "D" light fixtures to Outdoor Lighting Code compliance table. SHEET E1.1 1. See note 1 for sheet MP1 above. This sheet and panel schedule may need revision. Reviewer: Christopher Anderson, Pima County Development Services May 20, 2016 |
05/23/2016 | PIMA COUNTY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | SHEET MP2 1. Delete references to 2006 UPC on Plumbing Fixture Schedule. Current adopted Code is 2012 IPC. Reviewer: Christopher Anderson, Pima County Development Services May 20, 2016 |
05/23/2016 | PIMA COUNTY | BUILDING-COMMERCIAL | REVIEW | Reqs Change | GENERAL 1. Sheets S-1.0, S-1.1, S1.2, and S-6.1 have not been included in the drawing set. Please provide for review. 2. Delete Sheet S-3.0 marked "Preliminary Not for Construction" on the engineer's seal. 3. The amount and labeling of architectural sheets does not match the Sheet Legend. SHEET A-12 1. Remove "EX @ 125 CFM" from plan 2/A-12. Exhaust fan schedule on sheet MP1 has different value. STRUCTURAL CALCULATIONS 1. No calculations for fabricated beam seats are included in calculations package. Reviewer: Christopher Anderson, Pima County Development Services May 20, 2016 |
05/23/2016 | PIMA COUNTY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | SHEET MP1 1. Architectural roof plan, roof framing plan and electrical plan all indicate 8 (1000-lb) mechanical units on the roof. MP1 indicates 4 evaporative coolers. Revision to this sheet may be required. Reviewer: Christopher Anderson, Pima County Development Services May 20, 2016 |
05/23/2016 | CPIERCE1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
05/24/2016 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | CDRC TRANSMITTAL TO: Development Services Department Plans Coordination Office FROM: David Rivera for Steve Shields PDSD Zoning Review PROJECT: Produce Warehouse Building Review T16CM03297 Related to DP16-0075 TRANSMITTAL DATE: May 24, 2016 DUE DATE: June 3, 2016 COMMENTS: Please resubmit revised drawings and any redlined plans along with a detailed response letter, which states how all Zoning Review Section comments were addressed. 1. Zoning has reviewed the building plans as it relates to the zoning review purview. While the building plans are consistent with the zoning DP Zoning cannot approve the building plans until the DP is approved. 2. If the long term bicycle parking facility is to be placed within the building include a fully dimensioned detail drawing of the location and facility. See UDC section 7.9.4 for design criteria. 3. Zoning will review the building plans on the next submittal and compare the building plans to the Approved DP as it relates to the zoning purview |
05/26/2016 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Reqs Change | Can not be approved until DP 16-0075 is approved. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
05/31/2016 | CPIERCE1 | OUT TO CUSTOMER | Completed |