Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T16CM02015
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/22/2016 | MARTIN BROWN | FIRE | REVIEW | Approved | |
04/05/2016 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide structural calculations for the mounting shelf for the water heater to show that the water heater will be safely supported from the building structure. Reference: Section 301.2, IPC 2012. |
04/05/2016 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012, and Section 312.1, IMC 2012. |
04/05/2016 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Reqs Change | DATE: April 5, 2016 DUE DATE: April 15, 2016 SUBJECT: TI - White Box TO: Gene Goldstein LOCATION: 1785 W Valencia Road REVIEWERS: Paul Baughman, PE, CFM ACTIVITY: T16CM02015, T16CM02016 and T16CM02017 SUMMARY: Engineering Division of Planning and Development Services Department has received and reviewed the proposed Development Plan Package. The following items need to be addressed: 1) Per AM 2-06.4.3 please list the DP15-0126 and T16CM02015, T16CM02016 or T16CM02017 numbers on the plan. 2) Per AM 2-06.4.9A draw in all lot lines with approximate distances and measurements of the proposed structures and from the proposed structures to the lot lines as part of the site plan. This will allow a review of the proposed construction to verify conformance with the development package site layout. If you have any comments questions or wish to discuss new information, please call or email me at 520-837-5007 or paul.baughman@tucsonaz.gov. |
04/05/2016 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | Tucson Water expects the water pressure range for this address to be 47.6 to 54.6 PSI. |
04/07/2016 | BROWN & ASSOCIATES | BUILDING-COMMERCIAL | REVIEW | Reqs Change | ARCHITECTURAL COMMENTS General 1. Comments may be made on only one specific sheet but shall apply at all similar conditions. Reference IBC Section 107.2.1. 2. Please return redlined plans to Brown & Associates with resubmittal. White Box Tenant Improvement, Shop Space at Fry’s Shopping Center City of Tucson #: T16CM02015,16,17 April 6, 2016 Page 2 of 4 3. Written comments for the more critical issues have been provided, while numerous miscellaneous items have been noted on the red-marked prints/calculations. Each sheet that has red-mark comments is identified with a Red “X” in the lower right hand corner of the affected sheet. The respondent shall review all items and provide a written response to all comments (In those cases when only a redlined comment is provided, a response written adjacent to the red lined comment is acceptable) The red marked prints/calculations must be returned to Brown and Associates in order to complete the review process. The AOR shall acknowledge that all red lines had been properly dispersed to all the project consultants. Reference IBC Section 107.2.1. Sheet TS1 1. Project Code Review: Construction Type is identified as VN (Not Sprinkled). IBC 2012 recognizes Types VA and VB. Clarify and revise. Construction documents shall be of sufficient clarify to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of this code and relevant laws, ordinances, rules and regulations, as determined by the building official. Reference IBC Section 107.2.1. 2. General Notes: Note 23 references Fire Protection Sprinkler documents as a required separate submittal. Project Code Review indicates not sprinkled. Clarify and revise. Reference IBC Section 107.2.1. Sheet A1.1 1. Floor Plan: Enlarged Restroom Plan detail reference is mislabeled. Clarify and revise. Reference IBC Section 107.2.1. 2. Floor Plan Keynotes: Keynotes 1 through 5 reference Sheet A1.0. Sheet A1.0 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 3. Floor Plan General Notes: Note 5 references Sheet S3.4. Sheet S3.4 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 4. Ceiling Grid Detail 1: Bracing Wires note is missing. Clarify and revise. Reference IBC Section 1011.1. Sheet A1.2 1. Floor Plan: Enlarged Restroom Plan detail reference is mislabeled. Clarify and revise. Reference IBC Section 107.2.1. 2. Reflected Ceiling Plan: Exit signage not indicated at egress doors as required. Clarify and revise. Reference IBC Section 1011.1. 3. Floor Plan Keynotes: Keynotes 1 through 5 reference Sheet A1.0. Sheet A1.0 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 4. Floor Plan General Notes: Note 5 references Sheet S3.4. Sheet S3.4 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 5. Ceiling Grid Detail 1: Bracing Wires note is missing. Clarify and revise. Reference IBC Section 1011.1. Sheet A1.2 1. Floor Plan: Enlarged Restroom Plan detail reference is mislabeled. Clarify and revise. Reference IBC Section 107.2.1. 2. Floor Plan Keynotes: Keynotes 1 through 5 reference Sheet A1.0. Sheet A1.0 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 3. Floor Plan General Notes: Note 5 references Sheet S3.4. Sheet S3.4 is not included in the plan set. Clarify and revise. Reference IBC Section 1011.1. 4. Ceiling Grid Detail 1: Bracing Wires note is missing. Clarify and revise. Reference IBC Section 1011.1. Sheet A2.0 1. Enlarged Restroom Plan: Restroom Wall Elevation references are mislabeled. Clarify and revise. Reference IBC Section 107.2.1. 2. Restroom Elevation Keynotes: Keynote 5 indicates an 18’ Grab Bar instead of 18”. Clarify and revise. Reference IBC Section 107.2.1. ACCESSIBILITY COMMENTS 1. The accessibility portion has been reviewed and accepted. STRUCTURAL COMMENTS 1. The structural portion has been reviewed and accepted. |
04/07/2016 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please address the following electrical plan review comments. Also provide a written response. #1. Please show how the space numbers 101, 115, 129, correlate with the unit numbers on the floor plans. #2. Provide complete luminaire schedules. #3. Provide disconnects for the water heaters. #4. Indicate lighting and exhaust fan circuit controls. #5. Provide legends or symbol definitions on the plan documents. #6. Indicate feeder and branch circuit conduit, conductor, sizes and types for the electrical devices and equipment. Ref : 2012 IBC sec. 107.2.1, 2011 NEC |
04/08/2016 | STEVE SHIELDS | ZONING | REVIEW | Approved |