Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: T15PI00016
Parcel: Unknown

Address:
5650 E RIVER RD

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T15PI00016
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/17/2015 LINZUNZA UTILITY CLEARANCES COT STREETS DIVISION Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES PC WASTEWATER MGMT Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES QUEST COMMUNICATION Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES COX COMMUNICATION Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES SOUTHWEST GAS CORP Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES EL PASO NATURAL GAS Completed
07/17/2015 LINZUNZA UTILITY CLEARANCES KINDER MORGAN ENERGY Completed
07/23/2015 ZCANCHO1 DOT TRAFFIC REVIEW Approv-Cond July 23, 2015

SUBJECT: Rio Verde Village
PIA Plan T15PI00016

PROJECT REVIEWER: Zelin Canchola, TDOT Engineering Review Unit - Traffic Engineering


RESUBMITTAL REQUIRED: TDOT Traffic Engineering has reviewed the PIA Plan and recommends conditional approval once the right turn lane signs are shown on top of "Only sign"


1. Show "Right Lane" sign on top of "Only" sign as redlined on sheet 3 of 3.


If you have any questions I can be reached at 837-6659 or zelin.canchola@tucsonaz.gov
07/31/2015 GARY WITTWER DOT LANDSCAPE REVIEW Approved
08/12/2015 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Approv-Cond Date: August 12, 2015
PROJECT NAME: Rio Verde Village
PLAN #: U-2015-012
ACTIVITY NUMBER: T15PI00016
PROJECT REVIEWER: Jim Femling, City of Tucson DOT Streets & Traffic Maint.

Comments:

The TDOT Streets & Traffic Maintenance Division has reviewed the PIA Plan and recommends a conditional approval. The following comments need to be addressed prior to submitting the mylar plan set for final approval.

1. Provide a 4 inch pvc sleeve for irrigation under the new driveway approach.

If you have any questions, I can be reached at 791-3154 or james.femling@tucsonaz.gov
08/17/2015 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed
08/17/2015 LINZUNZA DOT ENGINEERING REVIEW Completed Date: August 17, 2015
PROJECT NAME: Rio Verde Village
PLAN #: I-2015-012
ACTIVITY NUMBER: T15PI00016
PROJECT REVIEWER: E. Craig Saltzman, Engineering Review Unit, City of Tucson DOT

Comments:

The TDOT Engineering Review Unit has reviewed the PIA Plan and recommends denial. The following comments need to be addressed prior to submitting the mylar plan set for final approval.

1. Sheet 2 of 3 - Typical Pavement Structural Section remove 2" ARAC and replace with 2" AC Mix #3.
2. Sheet 2 of 3 - Station 7+19 and station 9+29 remove Curb Access Ramp SD207(4A) and replace with Curb Access Ramp SD207(1). At all three access ramp locations include type 2 curb behind wheel chair landing.

If you have any questions, I can be reached at 837-6621 or Craig.Saltzman@tucsonaz.gov