Plan Number: T15PI00002
Parcel: Unknown

Address:
50 E BROADWAY BL

Review Status: Completed

Review Details: PIA - SUBMITTAL

Plan Number - T15PI00002
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/04/2015 LINZUNZA UTILITY CLEARANCES COT STREETS DIVISION Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES PC WASTEWATER MGMT Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES QUEST COMMUNICATION Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES COX COMMUNICATION Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES EL PASO NATURAL GAS Denied
02/04/2015 LINZUNZA UTILITY CLEARANCES KINDER MORGAN ENERGY Denied
02/18/2015 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Denied See redlines
02/18/2015 RICHARD LEIGH DOT ENGINEERING REVIEW Denied Comments by: Estevan Tineo 837-6646
Please see my comments below:

1. Sheet 1 of 3:

Please remove any references to City personal from City Notes. For example, note 4 (Sun Link Notes), should refer to DOT Engineering Permitting not Chris Leighton.

Sheet 2 of 3:

a. The new sidewalk area should consist of concrete sidewalk areas with brick bands, not brick sidewalk with concrete bands.

b. Plan view should indicate actual dimensions for separation between existing curbing and existing track slab.

c. For pedestrian safety, an handrail should be provided along the new curing alignment.

d. The proposed roof drain system should include clean-outs for future maintenance. In addition, please verify that the positive drainage will be provided.

e. Show existing striping and parking meters as applicable.


Sheet 3 of 3:

a. Show demolition limits needed to install proposed vertical curbing. Will the proposed curbing and improvements (including excavation needed to install curbing) impact any utilities, including SunLink underground power lines?

b. Detail 5: Indicate any new striping and relocated parking meters.
Esteban Carlos Tineo, P.E.
DOT Engineering Review
02/19/2015 GARY WITTWER DOT LANDSCAPE REVIEW Passed
02/26/2015 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Completed See additional comments from Sun Link and Park Tucson.
02/26/2015 JOSE ORTIZ DOT TRAFFIC REVIEW Passed
02/26/2015 LINZUNZA PIA COORDINATOR OUT TO CUSTOMER Completed See additional comments from Sun Link and Park Tucson.