Permit Number - T15CM08500
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/10/2015 MARTIN BROWN FIRE REVIEW Passed
12/18/2015 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. SHEET S0.1: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. PLEASE REVISE THE GENERAL CONSTRUCTION NOTES.
2. SHEET S2.1; FOUNDATION PLAN: A SLAB NOTE ON THE PLAN HAS A REFERENCE TO THE ACTUAL ELEVATION, BUT THE NOTE IS INCOMPLETE. PLEASE VERIFY.
3. SHEET S2.3 (ROOF PLAN NOTES); STRUCTURAL CALCULATIONS (DESIGN LOAD SCHEDULE): THE PLAN NOTE (#7) INDICATES A 6" CONCRETE PAD ON THE ROOF AT RTU LOCATIONS, WHILE THAT LOAD DOES NOT APPEAR IN THE DESIGN LOAD SCHEDULE. PLEASE VERIFY.
4. SHEET S2.3 (ROOF FRAMING PLAN); SHEET M2.1: PLEASE INDICATE THE ESTIMATED RTU LOCATIONS ON THIS PLAN (REFERENCE PRELIMINARY SHEET M2.1).
5. SHEET S3.0; DETAILS AT SUMP: PLEASE INDICATE ON THE PLAN WHERE THE SUMP PIT IS LOCATED IN THE ELEVATOR PIT.
6. SHEET S3.0; DETAIL AT SITE RETAINING WALL: WERE STRUCTURAL CALCULATIONS SUBMITTED FOR THIS WALL DESIGN? IS IT PART OF THIS PERMIT? PLEASE VERIFY.
7. SHEETS S3.0, S4.0, AND S4.1: PLEASE NUMBER THE DETAILS AND INDICATE ON THE APPROPRIATE PLAN WHERE THOSE DETAILS ARE CUT.
8. GENERAL: ALL STRUCTURAL DRAWINGS FOR THIS SUBMITTAL SHALL HAVE THE SEAL OF THE ENGINEER OF RECORD DATED. IN ADDITION, THE EXPIRATION DATE OF THE LICENSE MUST BE INDICATED BELOW THAT SEAL.
9. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
12/21/2015 ERIC NEWCOMB PLUMBING-COMMERCIAL REVIEW Passed
12/21/2015 ERIC NEWCOMB ELECTRICAL-COMMERCIAL REVIEW Passed
12/21/2015 ENEWCOM1 WATER REVIEW Passed
12/21/2015 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
12/21/2015 ERIC NEWCOMB MECHANICAL-COMMERCIAL REVIEW Passed
12/30/2015 MICHAEL ST. PAUL ZONING REVIEW Reqs Change Approval of DP15-0204 is required for building approval by the zoning review section.
12/30/2015 ELIZABETH LEIBOLD ENGINEERING REVIEW Reqs Change Needs DP15-0204 approval first.

Final Status

Task End Date Reviewer's Name Type of Review Description
01/12/2016 AROMERO4 OUT TO CUSTOMER Completed