Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T15CM08041
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/24/2015 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 12/02/2015 | ROBERT SHERRY | WATER | REVIEW | Completed | |
| 12/03/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | The 2012 International Energy Compliance Code is the relevant energy code for this project, not the 2012 IRC. Revise the "R and U Values" information on sheet TS.1 to reflect the actual components being installed in the proposed shell building. Note that all fenestration shall be NFRC-certified. |
| 12/03/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide roof drainage calculations and dimensions of the scuppers and downspouts. Provide overflow protection for the roof. Reference: Sections 1101, 1106 and 1108, IPC 2012. |
| 12/09/2015 | PAUL BAUGHMAN | ENGINEERING | REVIEW | Reqs Change | DATE: December 9, 2015 DUE DATE: December 16, 2015 SUBJECT: New Retail Shell Building TO: Gene Goldstein, RE LOCATION: 3520 S 6th Avenue REVIEWERS: Paul Baughman, PE, CFM ACTIVITY: T15CM08041 SUMMARY: Engineering Division of Planning and Development Services Department has received and reviewed the proposed Development Plan Package. The following items need to be addressed: 1) Please update elevation keynotes 12 and 13 on sheet A2 to reflect callout locations for keynotes 13 and 14. 2) A subsequent submittal of a geotechnical report may result in additional comments if warranted. 3) Approval of DP15-0200 is required prior to approval of this submittal. If you have any comments questions or wish to discuss new information, please call or email me at 520-837-5007 or paul.baughman@tucsonaz.gov. |
| 12/11/2015 | STEVE SHIELDS | ZONING | REVIEW | Reqs Change | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: New Retail Building @ 3520 S. 6th Avenue T15CM8041 Building Plan (1st Review) TRANSMITTAL DATE: December 11, 2015 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning has reviewed the building plan for compliance with development package DP15-0200. The plans appear to match the development package but Zoning cannot approve until all other PDSD review agencies have approved the plan. 3. Until the above comments have been addressed and all other PDSD review agencies have approved the building plans zoning cannot approve. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
| 12/14/2015 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET TS.1; SHEET INDEX: PLEASE ADD THE STRUCTURAL SHEETS TO THE INDEX. 2. SHEET TS.1; SHEET INDEX: THE SCHEDULES AND DETAILS LISTED ON A.4 SHOULD BE MOVED TO A.5, AND THE WALL SECTIONS LISTED ON A.5 SHOULD BE MOVED TO A.4. 3. SHEET A.1; FLOOR PLAN: PER THE SITE PLAN ON SHEET TS.1, THE SOUTH WALL OF THE BUILDING IS LESS THAN FIVE FEET FROM THE PROPERTY LINE. PER THE IBC TABLE 602, THIS WALL MUST HAVE A MINIMUM TWO HOUR FIRE RESISTANCE RATING. PLEASE INDICATE ON THE DRAWINGS THE UL LISTING THAT MEETS THE TWO HOUR REQUIREMENT, AND SHOW A DETAIL FOR THAT WALL. 4. SHEET A.2; ROOF PLAN: PLEASE REVISE THE TITLE FROM 'WEST ELEVATION' TO ROOF PLAN. 5. SHEET A.2; WEST ELEVATION: THE SECTION CUT REFERENCES 2/A.3. PLEASE REVISE THE REFERENCE NUMBER. 6. SHEET A.3; SECTION KEYNOTES: NOTE 16 REFERENCES DETAIL 4/A.3. PLEASE REVISE THE REFERENCE NUMBER. 7. SHEET A.3; SECTION KEYNOTES: PLEASE FINISH THE DETAIL REFERENCE IN NOTE 3. 8. SHEETS S.1 THROUGH S.4: THESE SHEETS MUST BE STAMPED, SIGNED, AND DATED BY THE ENGINEER OF RECORD, OR A STATEMENT OF GENERAL CONFORMANCE OF THE DRAWINGS TO THE STRUCTURAL CALCULATIONS MUST BE INCLUDED ON EACH SHEET. THIS STATEMENT MUST BE STAMPED, SIGNED, AND DATED BY THE ENGINEER OF RECORD. 9. SHEET S.1; CARPENTRY NOTES: NOTE 1f REFERENCES THE 2003 IBC. PLEASE REVISE. 10. SHEET S.2 (FOUNDATION PLAN); STRUCTURAL CALCULATIONS (SHEET 12): THE CALCULATIONS INDICATE FOOTING F-1 (INTERIOR COLUMNS) TO BE 4'-4" SQUARE WITH 5-#5 EACH WAY, WHILE THE PLAN INDICATES 4'-0" SQUARE WITH 5-#5 EACH WAY. PLEASE COORDINATE. 11. SHEET S.4 (DETAIL 5); STRUCTURAL CALCULATIONS (SHEET 9): THE LEDGER CALCULATION INDICATES A 3X LEDGER WITH 5/8" DIAMETER ANCHOR BOLTS AT 16" OC, WHILE DETAIL 5 INDICATES A 3X12 LEDGER WITH 1/2" ANCHOR BOLTS AT 48" OC. PLEASE COORDINATE. 12. SHEET S.4 (DETAILS 4 AND 5); STRUCTURAL CALCULATIONS (SHEET 18): THE CALCULATIONS INDICATE 1/2" PLLYWOOD ROOF SHEATHING, WHILE THE DETAILS INDICATE 1/2" OSB SHEATHING. PLEASE COORDINATE. 13. SHEET S.4; AWNING DETAIL: PLEASE PROVIDE STRUCTURAL CALCULATIONS FOR THE AWNING DESIGN AND SUPPORT. 14. STRUCTURAL CALCULATIONS: THE CALCULATIONS NEVER INDICATE THE BLOCK WALL REINFORCING REQUIREMENTS. PLEASE ADD. 15. GENERAL: THE STRUCTURAL DRAWINGS NEVER INDICATE THE ROOF DECK NAILING PATTERN. PLEASE ADD. 16. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 12/15/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please provide full compliance with the Tucson / Pima County Outdoor Lighting Code. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/07/2016 | EGALLET1 | OUT TO CUSTOMER | Completed |