Permit Number: T15CM07949
Parcel: 14118610A

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T15CM07949
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
11/19/2015 MARTIN BROWN FIRE REVIEW Approved
12/02/2015 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change Termination of the excess pressure relief from the water heater over an elevated service sink is not approved location. Reference: Section 504.6 (6), IPC 2012.
12/02/2015 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Completed
12/02/2015 ROBERT SHERRY WATER REVIEW Completed
12/09/2015 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
12/14/2015 LOREN MAKUS ENGINEERING REVIEW Reqs Change Development Package must be approved first.
12/15/2015 DAVID RIVERA ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: David Rivera
Principal Planner

PROJECT: T15CM07949
9056 S Houghton Road
Building Plan Review
Brake Masters - Automotive Major Service and Repair Use

TRANSMITTAL DATE: December 15, 2015

COMMENTS: Please resubmit building drawings along with redlines and a response letter, which states how all Zoning Review Section comments were addressed, if any.

1. Zoning has reviewed the building plan for compliance with the current DP (Development Package) site plan and the zoning requirements as they apply to the building. While the building plans are in substantial compliance with the DP as it relates to the zoning review purview, zoning cannot approve the building plans at this time.

As of this review date the DP has not been approved by all CDRC/PDSD plan reviewers so technically the building plan cannot be approved by zoning at this time.

2. Zoning will re-review the building plans on the next submittal and compare them to the approved site plan if available. Zoning is willing to review the building plans over the counter and approve them if the development package is approved and available for comparison.

3. Ensure that the DP plan sheets that have been included in the building plans package are updated with the most current or approved DP plan sheets on the next building plan submittal.

If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.
12/17/2015 CLAYTON TREVILLYAN BUILDING-COMMERCIAL REVIEW Completed
12/17/2015 CTREVIL1 COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed

Final Status

Task End Date Reviewer's Name Type of Review Description
01/06/2016 KROBLES1 OUT TO CUSTOMER Completed