Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T15CM05668
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/13/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Comment not addressed. [Initial comment: Verify that the HVAC unit controls provide for an automatic start capability. Reference: Section C403.2.4.3.3, IECC 2012.] 2. Comment not addressed. [Initial comment: Provide structural calculations and details to demonstrate that the installation of the new rooftop unit will not adversely affect the structural integrity of the roof. Reference: Section 302.1, IMC 2012.] 3. Show how the outside air will be filtered during normal and economizer operation if the filters are located in the return air grills. Note also that duct smoke detectors are to be located in the return air stream prior to outside air inlets and filters (see Section 606.2.1, IMC 2012). [Initial comment: A note on sheet AM-1 indicates that no filters are to be located in the rooftop units but are instead to be located in return air grilles. Show that this arrangement of the filters is in accordance with the conditions of the equipment listing and the manufacturer's installation requirements. Reference: Section 304.1, IMC 2012.] |
10/13/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. The expansion tank information on sheet AP-2 is reasonable but detail 1/AP-4 calls for a much larger expansion tank; coordinate the size of the expansion tank. [Initial comment: Provide calculations for the size of the expansion tank for the water heater and show how the specified expansion tank is to be supported. Reference: Section 607.3, IPC 2012.] 2. Comment not addressed. Note that there are only four chapters in the commercial part of the 2012 IECC. [Initial comment: Revise the "2012 IECC Compliance Notes" on sheet AP-4 to reference the correct sections of the 2012 edition of the IECC.] 3. Revise the location of the vacuum relief valve shown in detail 11/A-7 per the manufacturer's installation instructions. The vacuum relief valve is to be located between the shut off valve and the hot water storage tank. |
10/13/2015 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | Neither the water meter nor the backflow preventer may be located within the building but are required to be located where they are accessible to Tucson Water. Show the actual location of the meter and the backflow preventer. Note that Tucson Water does not provide a 1-1/4" water meter. [Initial comment: Provide the size of the water meter serving this suite, the size of the backflow preventer associated with the water meter, and the total water demand served by the water meter. Reference: Section 107.2.1, IBC 2012.] |
10/14/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
10/14/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
10/26/2015 | CLAYTON TREVILLYAN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | BUILDING APPROVAL PENDING MECHANICAL COMMENTS |