Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T15CM05250
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/31/2015 | CLAYTON TREVILLYAN | BUILDING-COMMERCIAL | REVIEW | Completed | |
08/31/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Plan Sheet PV 1, note 2 of the riser diagram notes, allows for a bus tap option at the Utility interconnection in the main distribution panel. Please provide a detail or drawing to accomodate this option. Also include the fused disconnect switch location ( should be as close as possible to the Main Switchboard ). Provide for a third party NRTL field inspection , and approval to maintain the Listing of the equipment. Ref: IBC sec.107.2.1. NEC art. 110, 230.66, 690, 705. |
09/01/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/14/2015 | AROMERO4 | OUT TO CUSTOMER | Completed |
09/10/2015 | FERNE RODRIGUEZ | REJECT SHELF | Completed |