Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T15CM05115
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/30/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
08/06/2015 | CLAYTON TREVILLYAN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | BUILDING PLAN REVIEW COMMENTS Date: 8-7-15 Activity: T15CM05115 Address: 333 E Wetmore Rd Applicant: Metro TED This letter reflects comments to be addressed. The purpose of this review is to verify compliance to the 2012 International Building Code and local amendments. In order to facilitate a shorter back check time, we request that you please provide two complete sets of revised plans and calculations, along with a written response to each of the noted items indicating action taken. Other comment references may be derived from additional codes and standards adopted by The City of Tucson. All features have been checked only to the extent allowed by the submittals provided for review. All portions of this project are assumed to meet other departmental requirements, conditions and concerns before permit approval. Sheets A-201/2 1. Please indicate existing or new 2-hour fire-resistance rating for enclosure walls surrounding interior exit stairways and elevator shafts, 713.4, 1022.2. Sheet M3.00 2. Specify the proposed support and attachment for suspended mechanical equipment, 107.2. Sheet E1.02 3. Provide emergency egress illumination for rooms 600 and 602, 1006.3. Sheets E3.01/2 4. Please specify the two-way communication system for the elevator areas on each floor, 1007.8. If you have any questions please contact: Clayton Trevillyan, CBO 520.837.4913 Clayton.Trevillyan@tucsonaz.gov |
08/06/2015 | ROBERT SHERRY | WATER | REVIEW | Completed | |
08/07/2015 | CTREVIL1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/13/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Provide pressure-absorbing devices for the water connections to appliances equipped with quick-acting or solenoid valves (e.g. ice makers). The pressure-absorbing devices shall conform to ASSE 1010; an air chamber is not acceptable. Reference: Section 604.9, IPC 2012. 2. Show the water supply and backflow preventers for the tenant-supplied appliances that are directly-connected to the water supply. Reference: Sections 606.1 608.1 and 608.3, IPC 2012. 3. Verify the need for an indirect waste receptor for the ice maker and ice bin. Reference: Section 802.1.3, IPC 2012. |
08/14/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
08/18/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please provide full compliance with the IECC for the interior lighting. |