Review Details: COMMERCIAL - TI
Permit Number - T15CM04503
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/13/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
07/14/2015 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
07/16/2015 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
07/20/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the location of the shut off valve for the water heater in Detail 2/P4.1 to be upstream of the sediment trap, as close to the equipment as possible. Reference: Section 408.4, IFGC 2012. 2. Coordinate the type of vents to be used for the water heater; the plumbing specification calls for a concentric vent while the mechanical plans call for a two-pipe vent and intake system. Reference: Section 107.2.1, IBC 2012. 3. Revise the label for the water heater in detail 2/P1.2; it is currently labeled as a hose bibb. Reference: Section 107.2.1, IBC 2012. 4. Provide tempered water for the restroom lavatories using approved devices conforming to ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2012. 5. Show the drain piping for P-9 and the new mop sink P-4 in detail 2/P1.2. Reference: Section 107.2.1, IBC 2012. 6. On the waste and vent diagram, the drain for sink P-7, located on the second floor, appears to connect to the building drain serving the first floor. Revise the drain to so that it does not pass through the backwater valve. Reference: Section 715.1, IPC 2012. 7. Coordinate the type of vents to be used for the water heater; the plumbing specification calls for a concentric vent while the mechanical plans call for a two-pipe vent and intake system. Reference: Section 107.2.1, IBC 2012. |
07/20/2015 | ROBERT SHERRY | WATER | REVIEW | Completed | |
07/21/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Completed | |
07/24/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Please provide the following information. #1. Compliance with the Tucson Outdoor Lighting Code sec. 402.1. For exterior lighting. #2. Full compliance with the IECC for the interior lighting. #3. Provide additional information ( spec's ) for the transfer switch, voltage , phase, amp rating. |
07/31/2015 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET G1.0; EXITING DIAGRAMS: THE DIAGRAMS DO NOT FOLLOW THE REQUIREMENTS OF THE IBC SECTION 1016.3 FOR MEASUREMENT OF THE EXIT ACCESS TRAVEL DISTANCE. PLEASE REVISE. 2. SHEET G1.0; EXITING DIAGRAMS: PLEASE INDICATE ON THE PLANS THE NUMBER OF OCCUPANTS USING EACH EXIT AND THE EXIT WIDTH/STAIR WIDTH REQUIRED FOR EACH. 3. SHEET G1.0; SECOND FLOOR PLAN: PLEASE VERIFY ON THE PLAN THE EGRESS BALCONY MEETS THE REQUIREMENTS OF THE IBC SECTION 1019.4 FOR LOCATION. 4. SHEET G1.0; FLOOR PLANS: PLEASE VERIFY ON THE PLANS THE EXTERIOR STAIRWAYS MEET THE REQUIREMENTS OF THE IBC SECTION 1026.5 FOR LOCATION. 5. SHEET G1.0; SECOND FLOOR PLAN: PLEASE INDICATE ON THE PLAN THE EXTERIOR AREAS FOR ASSISTED RESCUE. VERIFY ON THE DRAWINGS THE REQUIREMENTS OF THE IBC SECTION 1007.7 ARE MET FOR THE AREAS OF ASSISTED RESCUE, INCLUDING SIZE, SEPARATION, AND OPENNESS. 6. SHEET G1.0; SECOND FLOOR PLAN: PLEASE VERIFY ON THE PLAN THE EXTERIOR STAIRS THAT ARE PART OF THE MEANS OF EGRESS MEET THE REQUIREMENTS OF THE IBC SECTION 1007.7.6 FOR CLEAR WIDTH. 7. SHEET G1.0; SECOND FLOOR PLAN: PLEASE VERIFY ON THE PLAN THE REQUIREMENTS OF THE IBC SECTION 1007.8 ARE MET FOR TWO-WAY COMMUNICATIONS SYSTEM AT THE ELEVATOR LANDING OR AREAS OF ASSISTED RESCUE. 8. SHEET G1.0; SECOND FLOOR PLAN: PLEASE VERIFY ON THE PLAN THE REQUIREMENTS OF THE IBC SECTIONS 1007.9, 1007.10, AND 1007.11 ARE MET FOR AREAS OF ASSISTED RESCUE SIGNAGE. 9. SHEET G1.0; SECOND FLOOR PLAN: PLEASE VERIFY ON THE PLAN THE REQUIREMENTS OF THE IBC SECTION 1018 ARE MET FOR CORRIDORS, INCLUDING FIRE RESISTANCE RATING, WIDTH, AND CONTINUITY. 10. SHEET G1.0; FLOOR PLANS: PLEASE VERIFY ON THE PLANS THE REQUIREMENTS OF THE IBC SECTION 3411.6 ARE MET FOR ACCESSIBILITY ISSUES IN EXISTING BUILDINGS. 11. SHEET G1.0; FLOOR PLANS: PLEASE VERIFY ON THE PLANS THE REQUIREMENTS OF THE IBC SECTION 1006 ARE MET FOR ILLUMINATION LEVELS AND EMERGENCY POWER FOR ILLUMINATION. 12. SHEET G1.0: PLEASE INDICATE ON THE DRAWINGS HOW THE MAXIMUM 20% OF THE TENANT IMPROVEMENT COST FOR ACCESSIBILITY ISSUES PER THE IBC SECTION 3411.7(EXCEPTION 1) IS MET. 13. SHEET S1.0; STRUCTURAL NOTES (PRE-MANUFACTURED STEEL STAIRS): PLEASE COMPLETE THE SECOND NOTE. 14. SHEET S2.0 (HEADER SCHEDULE); STRUCTURAL CALCULATIONS (PAGE 22): PLEASE CORDINATE THE HEADER CALCULATIONS DH1, DH2, DH3, AND DH4 WITH THE HEADER SCHEDULE ON SHEET S2.0. 15. SHEET S3.1; DETAIL 205: A NOTE ON THE LOWER RIGHT OF THE DETAIL AT THE HSS 4X3X1/4 HAS AN UNFINISHED DETAIL REFERENCE. PLEASE COMPLETE. 16. STRUCTURAL CALCULATIONS; PAGE 52: THE LATERAL DESIGN CALCULATIONS INDICATE THE NEW BUILDING ADDITIONAL WEIGHT AND THE NEW BUILDING ADDITIONAL WIDTH INCREASE THE EXISTING BUILDING ONLY BY 7% AND 6%, THEREFORE THE DEMAND-CAPACITY RATION IS LESS THAN 10%, SO THAT ANALYSIS IS EXEMPT PER THE IEBC SECTION 807.5. THAT SECTION ALSO INCLUDES THE VERBIAGE "IN ADDITION, THE ALTERATION SHALL NOT CREATE A STRUCTURAL IRREGULARITY PROHIBITED BY ASCE 7 UNLESS THE ENTIRE STRUCTURE COMPLIES WITH SECTION 301.1.4.2." DOES THE ALTERATION MEET THOSE CRITERIA? PLEASE VERIFY. SECTION 3403 OF THE IBC OFFERS A SIMILAR APPROACH. 17. STRUCTURAL CALCULATIONS; PAGE 52: THE BUILDING DIAGRAM INDICATES A NEW SHEARWALL LOCATED 6' FROM THE EXISTING STRUCTURE (GRID LINE 1 ON SHEET S2.0). THAT SHEARWALL DOES NOT SHOW UP ON SHEET S2.0. PLEASE VERIFY. 18. STRUCTURAL CALCULATIONS; PAGE 2: UNDER 'DESCRIPTION OF STRUCTURE', A NOTE INDICATES "WE ARE ASSUMING THE NEW MECHANICAL UNITS DO NOT EXCEED THE WEIGHT OF THE EXISTING MECHANICAL UNITS". PLEASE VERIFY ON THE DRAWINGS. 19. SHEET A2.2; SECOND FLOOR PLAN: IN THE JANITOR'S ROOM, TWO KEY NOTES INDICATE 24. PLEASE REVISE. 20. SHEET A2.3; ELEVATION 2: THE KEY NOTE 37 AT THE DOOR ON THE LEFT IS INCORRECT. PLEASE REVISE. 21. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
08/06/2015 | FRODRIG2 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | PER ERIC NEWCOMB |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
08/07/2015 | EGALLET1 | APPROVAL SHELF | Completed |
08/07/2015 | EGALLET1 | OUT TO CUSTOMER | Completed |
08/07/2015 | EGALLET1 | REJECT SHELF | Completed |