Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T15CM03577
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 06/03/2015 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 06/16/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | #1.Please provide warning labels on the service equipment and the J-Box used for the line side tap as required per 690.54 and 705.10 NEC. #2. Show wiring methods from canopy location to existing service location. Is it wire in EMT conduit per the one line and three line diagrams ? |
| 06/25/2015 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET DP1; SITE PLAN: IT IS NOT CLEAR FROM THIS PLAN THAT THE SETBACKS FOR THE PARKING STRUCTURE MEET THE REQUIRED DISTANCES. THE ROOF OVERHANG IS ALLOWED TO BE 2'-0" MINIMUM FROM THE PROPERTY LINE, AND THE SUPPORT COLUMN MUST BE A MINIMUM OF 5'-0" (TO THE COLUMN FACE) FROM THE PROPERTY LINE. PLEASE VERIFY. 2. SHEET S-2; ELEVATION: PLEASE PROVIDE STRUCTURAL CALCULATIONS FOR THE CONNECTION OF THE COLUMN TO THE BEAM, AND THE COLUMN TO THE FOUNDATION. 3. SHEET S-4; CAISSON FOUNDATION SECTION: AT THE COLUMN BASE, CLARIFY THE CONNECTION. WHAT MEMBER EXTENDS INTO THE FOOTING AND EXTENDS 1'-0" ABOVE GRADE AND IS CONNECTED TO THE COLUMN (LIST THE SLEEVE GAGE)? INDICATE THE SLEEVE IS ON TWO SIDES OF THE COLUMN. 4. SHEET S-4; MIDDLE BEAM PURLIN CONNECTION SECTION: INDICATE ON THE SECTION THE CONNECTION OF THE PURLIN TO THE BEAM. 5. STRUCTURAL CALCULATIONS: NO CALCULATIONS WERE LOCATED FOR THE FOUNDATION DESIGN. PLEASE PROVIDE. 6. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |