Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T15CM03177
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/12/2015 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
05/12/2015 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
05/12/2015 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET T1; CODE REVIEW CHECKLIST: THE OCCUPANCY IS LISTED AS EDUCATIONAL. PLEASE REVISE TO 'TRAINING AND SKILL DEVELOPMENT'. 2. SHEET T1; CODE REVIEW CHECKLIST: THE OCCUPANT LOAD INDICATES THE NET CLASSROOM AREA IS 760 SF, WHILE THE 'TENANT SPACE' ABOVE INDICATES 971 SF. EXPLAIN THE DIFFERENCE ON THE DRAWINGS. 3. SHEET T1; CODE REVIEW CHECKLIST: HOW WAS THE OCCUPANT LOAD OF 8 DETERMINED FOR THE OFFICES (373 SF IS INDICATED)? PLEASE VERIFY ON THE DRAWINGS. 4. SHEET T1; EXIT PLAN: VERIFY THE DEAD END CORRIDOR (CORRIDORS 107 AND 109) MEET THE REQUIREMENTS OF THE IBC SECTION 1018.4(2). 5. SHEET A2; FLOOR PLAN: NEW INTERIOR PARTITIONS HAVE A DETAIL 1/A1 INDICATED. PLEASE REVISE THE SHEET REFERENCE. 6. GENERAL: PLEASE PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
05/12/2015 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
05/13/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the ventilation calculations, using "beauty salon" instead of "classroom". AC-2 is also serving part of the same area. Note that general exhaust of 0.60 cfm/square foot is required for a beauty salon. 2. The zone air distribution effectiveness (Ez) for a gas pack with ceiling supply and ceiling return is 0.8. |
05/13/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
05/13/2015 | MARTIN BROWN | FIRE | REVIEW | Approved | |
05/13/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Verify the type of existing water closets: flush valve or flush tank. 2. Provide a drinking fountain. 3. Provide the developed pipe lengths from each gas-fired appliance to the gas meter. 4. Calculate the hot water demand and determine if the specified water heater will meet the demand. 5. If PEX tubing is to be allowed, provide a chart indicating the sizes to be used compared to the type M copper. 6. Verify that the tankless water heater requires an expansion tank. |
05/13/2015 | ROBERT SHERRY | WATER | REVIEW | Reqs Change | Verify the total demand served by the existing water meter. |