Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T15CM02963
Parcel: 10922005H

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T15CM02963
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/03/2015 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. The water pressure calculations provide the allowable friction for the water pipes but the water velocity must also be limited to 8 feet per second. At 33 GPM, the water velocity in 1-1/2" PEX is nearly 9 feet per second. Clarify how the size of the PEX piping has been determined. [Second comment: Comment not addressed.] [Initial comment: Provide calculations showing how the PEX water supply tubing has been sized. Reference: Sections 604.1 and 604.3, IPC 201.]
2. Comment not addressed. [Second comment: Provide a civil site plan that shows the termination point of the primary roof drain.] [Initial comment: Clarify the termination point for the primary roof drain leader. Reference: Section 107.2.1, IBC 2012.]
08/13/2015 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change PER THE MECHANICAL COMMENTS, A DETAIL INDICATING HOW THE TYPE I HOOD WILL BE SUPPORTED FROM THE ROOF FRAMING SHOULD BE ADDED TO THE DRAWINGS. ALTHOUGH THE FRAMING WILL BE DESIGNED AS A DEFERRED SUBMITTAL, THE JOIST/TRUSS MANUFACTURER WILL NEED TO SEE A DETAIL FOR THE HOOD SUPPORT SO THE JOISTS/TRUSSES CAN BE DESIGNED TO INCLUDE THOSE ADDITIONAL LOADS.
08/14/2015 STEVE SHIELDS ZONING REVIEW Reqs Change PDSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Kneaders @ Rio Verde Village
T15CM2963
Building Plan (3rd Review)

TRANSMITTAL August 14, 2015

1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning will not approve until all other PDSD agencies have approved the building plan.

3. Until the above comments have been addressed and all other PDSD review agencies have approved the building plans zoning cannot approve.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
08/14/2015 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change This comment does not address the design of the trusses, just the connection of the hood to the trusses and the load that the trusses will support. No deferred submittal will be allowed for support of the kitchen hoods. [Second comment: There are no deferred submittals for the installation of kitchen hoods, show that the Type I hood is supported from the building structure in accordance with Section 507.6, IMC 2012.] [Initial comment: Provide structural calculations and details to show that the Type I hood is supported from the building structure in accordance with Section 507.6, IMC 2012 (the hood hanging weight plus the weight of personnel working in or on the hood). Reference: Section 302.1, IMC 2012.]
08/17/2015 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved
08/28/2015 ELIZABETH LEIBOLD ENGINEERING REVIEW Reqs Change Bldg plans may not be approved until dev pkg is approved.