Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T15CM02104
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/07/2015 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
| 04/13/2015 | JASON GREEN | ENGINEERING | REVIEW | Reqs Change | Building plan will be approved upon approval of the DP Package. |
| 04/15/2015 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. Please provide a copy of the latest site plan with submittal package. SHEET T2.1 2. Please provide a toilet fixture count for the total occupants and include results on drawings. 3. Please list all hazardous materials being used at this facility, their quantities, how they are being stored, where they are being used and how they are being transported as outlined in the 2012 IBC, Section 307 and as outlined in Tables 307.1 (1) and 307.1 (2). SHEET E-1 4. Please provide structural calculations for the extrerior lighting pole foundation. END OF REVIEW |
| 04/15/2015 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
| 04/20/2015 | MICHAEL ST. PAUL | ZONING | REVIEW | Reqs Change | Approval of DP15-0032 is required. The buildings plans (T15CM02104) must match the approved plans for the development package. |
| 04/20/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | AS per the comment on plan sheet E1.0, exception in the Tucson Outdoor Lighting sec.104.2 only relieves the requirements of subsections 2and 3. The Code still requires compliance for total lumen count to be within the maximum allowed and Lamp color temperature to comply with sec. 402.1. |
| 04/21/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. The floor plan on sheet A-2.0 still shows a new hand sink and eyewash unit (keynotes 27 and 29, sheet A-2.0) being installed where the service sink, P1, is located on sheet P-1.1. [Initial comment: Coordinate the number and type of new plumbing fixtures and emergency eyewash units to be installed with the architect. The floor plan on sheet A-2.0 shows a new hand sink and eyewash unit (keynotes 27 and 29, sheet A-2.0) being installed where the service sink, P1, is located on sheet P-1.1; and a new service sink and eyewash unit are being installed near column E-4 (keynotes 29 and 34, sheet A2.0).] 2. Correct the scupper calculations; a scupper is sized as a weir, not a horizontal pipe running full (i.e. Table 1106.3, IPC 2012 cannot be used to size scuppers). Provide overflow protection for the roof. [Initial comment: Provide roof drainage and hydraulic scupper size calculations based on the 100-year hourly rainfall rate for Tucson, 3" per hour. Provide overflow protection for the roof. Reference: Sections 1101, 1106 and 1108, IPC 2012, and Sections 1611.1 and 1611.3, IBC 2012.] |
| 04/21/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing (e.g. the roof doesn't appear to have any continuous insulation). Reference: Section C303.1, IECC 2012, as amended by the City of Tucson. 2. Provide NFRC fenestration product ratings for the U-factor and the SHGC values on COMcheck or use the appropriate default U-factor and SHGC values from Tables C303.1.3 (1), C303.1.3 (2) and C303.1.3.(3), IECC 2012. Reference: Section C303.1.3, IECC 2012. 3. Clarify the heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. The two heat pumps condition independent spaces but the load calculations appear to have combined the spaces. Include the doors in the heating and cooling load calculations. Reference: Sections C403.2.1 and C403.2.2, IECC 2012, and Section 312.1, IMC 2012. |
| 04/21/2015 | ROBERT SHERRY | WATER | REVIEW | Completed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/20/2015 | CPIERCE1 | OUT TO CUSTOMER | Completed |