Permit Number: T15CM02038
Parcel: 11714257C

Address:
564 S STONE AV

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T15CM02038
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/31/2015 CPIERCE1 WWM REVIEW Completed
04/02/2015 KEN BROUILLETTE FIRE REVIEW Approved
04/08/2015 RONALD BROWN BUILDING-COMMERCIAL REVIEW Reqs Change 1. Please provide a Site Plan showing all existing and new site improvements.
2. NOT USED
SHEET A1.1
3. The existing museum building already has a Certificate of Occupancy for a 3,160 s.f. building with an occupancy load of 242. Since no work is being completed here the existing CofO remains valid for that building.
4. A new Certificate of Occupancy will be issued for the remodeled residence change of use to the Holocaust History Display Center.
a. Please rework the code data analysis to include only the remodeled building. Please provide accurate square footage analysis and a new occupant load calculation for this building only.
c. Once the occupant load has been calculated, please recalculate the plumbing fixture requirements for this building only as the toilet rooms in the existing building are not handicap accessible from the outside and may not be used for toilets for the new facility.
b. This is also a change of use from duplex SFR (R3) to A3 Museum and is subject to impact fee charges.
5. Please add the following to Note 1: Accessible code requirements as per the 2012 IBC, Chapter 11 and the 2009 ICC A117.1.
SHEET A2
6. Please provide water dispensers as per the 2012 IBC, Section 1109.5 and the 2009 ICC A117.1, Section 602.
SHEET A6
7. At detail 4:
a. The toilet room is non compliant for 5'-0" turn around floor clearance, cuts too deep into the lavatory and negates the knee space height required by ICC A117.1, Section 306.3.
b. The break room does not allow for a 5'-0" turn around floor clearance.
5. At detail 3:
a. The 3'-5" wide ramp does not allow for handtrail clearance to provide for a code compliant 3'-0" minimum wide clearance between handrails.
b. To maintain a maximum slope of 1:12 the 28'-0" long ramp shopuld be 28'-5"
c. To maintain a 1:12 slope the undimensioned ramp should be 18'-10". Adding the dimensions on the opposite ramp, the numbers add up to 18'-4 5/8".
d. The strike jamb clearance at the door to the existing Jewish History Museum needs a 2'-0" clearance to the handrail.
e. The middle landing at the most northerly side has a 2.1% slope, 2% is maximum.
6. At detail 1, provide a 3'-0" clear dimension between the handrails.
7. At detail 2 provide width dimensions for all clearances between handrails with 3'-0" being the minimum.
END OF REVIEW
04/09/2015 RONALD BROWN COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
04/13/2015 DAVID RIVERA ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: David Rivera
Principal Planner

PROJECT: T15CM02038
564 S Stone Avenue
Interior Tenant Improvement Only - Museum

TRANSMITTAL DATE: April 20, 2015

DUE DATE: April 24, 2015

COMMENTS:

01. It is acknowledged that the amendment to the UDC to clarify "Cultural Use Class" is scheduled to go in front of Mayor and Council on April 21 and there is a 30 Day waiting period before the amendment becomes effective. Zoning will not be able to approve the permit until day after the 30 day waiting period has expired.

02. The intent to approve the site for a Cultural Use - Museum was hinged on the amendment to the UDC. The other important item to approval without full code compliance was to approve the "Museum Use" under the Zoning Compliance for Site Improvement under Section 3.3.3.H. Approval under the Zoning Compliance allows the Zoning Review Section to approve a permit application without imposing compliance with the sections listed in UDC 3.3.3.H.3. However the site must remain in the same configuration (Building/no demo or addition) to the building) as it appears in the 2005 Aerial. Exceptions to this requirement include restriping of the parking as listed in UDC section 3.3.3.H.8.

03. Per the plans, the rear part of the building is annotated as to be completely demolished. If this is the intent then the Zoning compliance cannot be used to approve the use. A change of use will require that additional documents be submitted for review including a development package.

04. The site is located in the GIID and could be used for this site if partial demo is intended. Review section 5.12.4 for requirements and development criteria.

05. The building is a Contributing structure within the Barrio Libre National Historic District and is listed as constructed in 1900. Prior to any demo of any portion of the building, a Historic review and approval will be required. Contact Michael Taku 837- 4963 for information on the HPZ review and process.

06. Provide any approved documents associated with the HPZ review and Demo approval with the next TI plans submittal. Provide intent related to the approval process whether zoning compliance under UDC 3.3.3.H, compliance with current code requirements or GIID overlay process will be used.

07. Based on the response to comment 6, additional plan review and process will be required. GIID or Current zoning compliance requires submittal a Development Package submittal for review and approval.

If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.
04/15/2015 ROBERT SHERRY WATER REVIEW Completed
04/15/2015 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Completed According to the note on sheet A1.1, "No work is to be done in the Jewish History Museum." If this is true, remove Keynote 46 from sheet A2. If the drinking fountains are to be added to the Jewish History Museum, show the specifications for the drinking fountains and show the water and drain piping on the plumbing drawings.
04/16/2015 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Demonstrate energy code compliance for the alterations to the building envelope based on the current code. Reference: Sections C101.4.3, C101.4.4, C101.5, and C103.2, International Energy Conservation Code 2012.
2. Alterations of an existing building in which the existing ceiling or wall cavities are exposed, shall have the exposed cavities filled with insulation. Reference: Section 101.4.3, exception 3, IECC 2012.
3. Specify the required U-factors and Solar Heat Gain Coefficients (SHGC) for the fenestration and doors on the architectural drawings. Provide the NFRC fenestration product ratings for the Solar Heat Gain Coefficient (SHGC) on COMcheck or use the appropriate default SHGC from Table C303.1.3 (2), IECC 2012. Reference: Section C103.2, IECC 2012.
4. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012, and Section 312.1, IMC 2012.
5. Show that adequate maintenance access space has been provided for the new heat pump in accordance with the manufacturer's installation instructions. Reference: Sections 304.1 and 306.1, IMC 2012.
6. Revise the ventilation calculations so that the total amount of ventilation air introduced by the HVAC unit is sufficient to supply the outside air required for transfer to the restroom as well as for ventilation of the other spaces being served by the HVAC unit. Reference: Section 403.2.2, IMC 2012.
04/17/2015 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Reqs Change Please provide feeder conduit and conductor sizes for panel "A". Also show location of panel "A" on the electrical floor plans. Ref: IBC sec. 107.2.1, NEC art.110.3, 300, 310.