Review Date Reviewer's Name Type of Review Description Status Comments
03/20/2015 RONALD BROWN BUILDING-COMMERCIAL REVIEW Reqs Change 1. Please rework the occupancy load calculations to include the following:
a. Altar 1/15
b. Multi Purpose Room 1/7
c. Nartix 1/5
d. Conference Room 1/15
e. Nurery 1/35
f. Business offices etc. 1/100
2. Door D-5 needs accessible strike clearances as per the 2009 ICC A117.1, Section 404.2.3.2.
3. Insure all exit doors have panic hardware as required by the 2012 IBC, Section 1008.1.10.
4. One urnial must have a 3'-0" wide stall as per the 2009 ICC A117.1, Section 605.3 and 305.
5. Change the accessibility code reference to the 2009 ICC A1171.1.
6. Please provide interior elevations of the receptionest counter, the break room sink cabinet and the nursery sink cabinet showing all accessibility requirements.
7. Please provide exterior elevations sheet 6. It is missing in one set
8. Please provide structural framing plans, details and calculations of the Alter/stage.
9. Please show the slope of the ramp to the altar.
END OF REVIEW
03/24/2015 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. The existing water heater is identified as being gas-fired in the Gas Demand Table on sheet P-1; include the gas piping serving the water heater on the plumbing plans. Reference: Section 107.2.1, IBC 2012.
2. Show how the gas pipe sizing conforms to Section 402.1 and 402.3, IFGC 2012; specifically, the gas pipe downstream of the branch serving AC-3 (labeled as 1" serving 240 CFH at 125 feet) and the common pipe serving AC units 5, 6, and 7 (labeled 1" serving 180 CFH at 125 feet).
3. Identify the owner-provided equipment that will be connected to the new wall boxes (keynote #13, sheet P1). Reference: Section 107.2.1, IBC 2012.
03/24/2015 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Demonstrate energy code compliance for the alterations to the building envelope based on the current code. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012.
2. Provide NFRC fenestration (i.e. doors and windows) product ratings for the U-factor and the SHGC values on COMcheck or use the appropriate default U-factor and SHGC values from Tables C303.1.3 (1), C303.1.3 (2) and C303.1.3.(3), IECC 2012. Reference: Section C303.1.3, IECC 2012.
3. Relocation of a packaged heat pump constitutes an alteration under the 2012 IECC and the unit shall conform to the provisions of the 2012 IECC. Reference: C101.4.3 and C202 (definition: alteration), IECC 2012.
4. The occupant load used to calculate the required ventilation is not necessarily the same as the occupant load used for calculating exiting requirements. The occupant load used for calculating the minimum required ventilation is to be based on Table 403.3, IMC 2012 or an approved engineering analysis of the specific occupancy type (i.e. provide an appeal to the building official). Reference: Section 403.3, IMC 2012.
03/26/2015 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
03/31/2015 AROMERO4 APPROVAL SHELF Completed
03/31/2015 AROMERO4 OUT TO CUSTOMER Completed
03/31/2015 AROMERO4 REJECT SHELF Completed