Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T15CM00155
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/07/2015 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | #1. As per comment #2 for lighting, it is still unclear as to which light fixtures are new, or existing, or existing relocated. Also circuiting not assigned or reflected on panel schedules. #2. Full compliance with IECC for interior lighting. |
04/07/2015 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Revise detail 1/P2 to show the hot water return pipe connecting to the cold water inlet to the water heater. See Section 607.2.2, IPC 2012. [Second comment: The proposed hot water recirculation system is not as described in Section 607.2, IPC 2012. Submit an appeal to the building official based on Section 316, IPC 2012 (Alternative Engineered Design), providing plans and documents to show that the proposed design is at least equivalent to the code-required system.] [Initial comment: Clarify the proposed hot water recirculation system and coordinate it with detail 1/P2. Reference: Section 107.2.1, IBC 2012.] |
04/07/2015 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the component descriptions to coordinate with the design drawings. [Second comment: Comment not addressed.][Initial comment: Provide energy code compliance calculations for the addition to the building envelope; use the climate zone for Tucson. Provide sufficient detail on the drawings to evaluate the energy compliance of the additions to the building envelope. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012.] 2. Complete the ventilation calculations as described in Section 403.3.2.3, IMC 2012. [Second comment: Revise the ventilation calculations using the methods described in Sections 403.3.1.1 through 403.3.1.3 and 403.3.2.3.1 through 403.3.2.3.4, IMC 2012.] [Initial comment: Provide calculations to show how ventilation will be provided for the occupied spaces. Reference: Section 401.2, IMC 2012.] 3. Comment not addressed. [Second comment: Comment not addressed.] [Initial comment: Show the location of the visible and audible signals for the duct smoke detectors. Reference: Section 606.4.1, IMC 2012.] |