Plan Review Detail
Review Status: Completed
Review Details: PIA - RESUBMITTAL
Plan Number - T14PI00011
Review Name: PIA - RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | COX COMMUNICATION | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | |
| 08/16/2016 | LINZUNZA | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | |
| 08/25/2016 | ZELIN CANCHOLA | DOT TRAFFIC | REVIEW | Reqs Change | August 11, 2016 ACTIVITY NUMBER: T14PI00011 PROJECT NAME: Silverbell Crossing PROJECT ADDRESS: N Silverbell road PROJECT REVIEWER: Zelin Canchola TDOT Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan therefore a revised plan is required for re-submittal. The following items must be revised or added to the plan. Include a response letter with the next submittal that states how all comments have been addressed. Sheet 2 of 10: 1. Revise note 39 from notes change the word "TO" to "NO". Sheet 5 and 10: 1. Add/Show no parking fire lane signs to cul de sacs: No Parking Begin Fire Access lane (12"x18") No parking Fire Access (12"x18") No parking End fire Access Lane (as"x18") 2. Add/Show Stop Signs at exit to Silverbell road. Add No Outlet sign. 3. Add Speed Limit sign 25 mph at entrance area to subdivision from silverbell road. 4. Show street name signs (locations). Note that shop drawings must be submitted to COT Traffic engineering prior to manufacturing. 5. List quantities and descriptions for striping materials including number and type of RPMs, lineal footage quantities of longitudinal and transverse striping, arrows, and words symbols. If you have any questions, I can be reached at 520 837 6659 or zelin.canchola@tucsonaz.gov |
| 08/29/2016 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Thanks for submitting the NPPO and coordinating with Silverbell construction. I see two median islands shown on the landscape plans that are not shown on the Civil plans. Please expalin. I also see dashed lines in the center of the roadway, which look like mainline to me. Please explain. |
| 09/13/2016 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | September 13, 2016 SUBJECT: Silverbell Crossing - Phase A, Paving Plans - T4PI00011 PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section RESUBMITTAL REQUIRED: TDOT Permits Section has reviewed the PIA paving plan and does not recommend approval at this time. The following comments need to be addressed in the subsequent review submittal. Please return redlined drawings with next submittal. Please reference PIA activity number on all correspondences. 1. Sheet1: Include Subdivision recordation information on cover sheet. 2. Sheet 1: Include the latest subdivision activity number on cover sheet. 3. Sheet 1: Include development plan activity number on cover sheet 4. Sheet 1: Provide Administrative address on cover sheet. 5. Sheet 4: Provide details of proposed stabilized surface treatment at the end of Dales Crossing Dr. The stabilized surface must be designed to support garbage trucks. 6. Sheet 4: Indicate placement of a concrete header per PC/COT SD 213 at the termination of pavement at the end of Dales Crossing Dr. 7. Sheet 3: Indicate the placement of midblock curb access ramps on Dales Crossing Dr. near station 15+00. 8. Sheet 5: Provide a section of the proposed slope protection along the cul-du-sac at the north end of Baby Bruno Way. 9. Sheet 6: Revise detail A1 to show a 6 (six) inch buffer between the sidewalk and property line. 10. Relocate the proposed curb access ramp between lots 62 and 63 west so it will be aligned directly across the ramp located on the NW corner of Baby Bruno Way and Baby Bruno Way - Entrance. 11. Submit geotechnical engineering evaluation and compaction reports for the imported fill placed throughout the site. 12. Sheet 3 & 5: Provide roadway profiles for the cul-de-sacs on Dales Crossing and Baby Bruno Way. Please Refer to redline plans for additional comments and comment details. If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsonaz.gov |
| 09/20/2016 | LINZUNZA | DOT PERMITS & CODES | REVIEW | Denied | Date: September 20, 2016 PROJECT NAME: Silverbell Crossing Phase A PLAN #: I-2014-011 ACTIVITY NUMBER: T14PI00011 PROJECT REVIEWER: Lance Peterson P.E., City of Tucson Engineering Inspections Comments: TDOT Engineering Inspection Unit has completed the review of the PIA plan and recommends resubmittal at this time. The following comments need to be addressed in the subsequent plan submittal. 1. Sheet 2 - Note 19 - Asphalt Concrete shall be new City of Tucson TDOT2 mix. 2. Sheet 7 - Detail H - I did not see a toe at the top of the grouted rip rap. Has this been evaluated? 3. Sheet 7 - Detail I - Asphalt should call out TDOT2 Mix If you have any questions, I can be reached at 837-6777 or Lance.Peterson@tucsonaz.gov |
| 09/21/2016 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | |
| 09/21/2016 | LINZUNZA | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 09/21/2016 | LINZUNZA | PIA COORDINATOR | OUT TO CUSTOMER | Completed |